Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Asso.subsea completes cable work at Croatian interconnector (Gallery)
Cabling

April 2, 2024 · about 2 years ago

Asso.subsea completes cable work at Croatian interconnector (Gallery)

Asso.subsea has completed the installation of approximately 30 kilometers of cables for the Adriatic Sea Islands Interconnection in Croatia, reaching depths of 70 meters. Asso.subsea transported and installed four distinct 110 kV cable systems, with the northern part connecting the landing sites Mal

1 minutes read
  • LinkedIn
  • X
  • Email
Asso.subsea completes cable work at Croatian interconnector (Gallery)
Source: Asso.subsea

Asso.subsea has completed the installation of approximately 30 kilometers of cables for the Adriatic Sea Islands Interconnection in Croatia, reaching depths of 70 meters.

Asso.subsea transported and installed four distinct 110 kV cable systems, with the northern part connecting the landing sites Mali Bok – Merag and Osor bay on the islands of Krk, Cres, and Lošinj, and the southern part linking Prapatna – Medvidbad and Travna – Slatina between the islands of Brač, Hvar, and Korčula.

The project was carried out in collaboration with contractor Končar on behalf of the Croatian transmission system operator (TSO) HOPS, and the activities were performed using the Atalanti cable laying vessel (CLV).

Source: Asso.subsea The replacement of old cables along these routes with 3x 630 mm2 submarine cables, totaling approximately 30,500 meters, was also executed.

The company noted that onshore pull-in activities needed preparation works before pull-in activities to all sites, which together with pull-in operation posed significant challenges, with two operations necessitating HDD pipes measuring around 120 and 60 meters in length, respectively.

Additionally, due to steep slopes with turns at various sites, Asso.subsea said it had designed and manufactured specific rollers. Gradients of up to 40% were encountered at locations such as Prapatna and Slatina.

Atalanti and pull-in teams onshore executed three consecutive landing activities.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingInterconnectorsSubseaBusiness & FinanceBusiness Developments & ProjectsOutlook & StrategyProject & TendersTransition

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Noble’s 2013-built drillship scoops up 10-well job in Africa with Tullow Oil
  2. 2North Sea appraisal ops up the oil & gas discoveries’ projected size
  3. 3Vantris Energy rakes in $441.8 million for Petronas and PTTEP offshore works in Malaysia
  4. 4CNOOC keeping Worley busy on its North Sea assets for five more years

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free