Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Subsea cable connecting DolWin epsilon platform to land installed
Cabling

July 24, 2025 · about 1 year ago

Subsea cable connecting DolWin epsilon platform to land installed

The laying of the subsea cable that connects the DolWin epsilon platform to land has been completed. The platform and the cables, part of TenneT’s DolWin5 grid connection, will transmit the electricity generated by Ørsted’s Borkum Riffgrund 3 offshore wind farm to the German grid on land. The DolWin

2 minutes read
  • LinkedIn
  • X
  • Email
Subsea cable connecting DolWin epsilon platform to land installed
Photo source: TenneT via LinkedIn

The laying of the subsea cable that connects the DolWin epsilon platform to land has been completed. The platform and the cables, part of TenneT’s DolWin5 grid connection, will transmit the electricity generated by Ørsted’s Borkum Riffgrund 3 offshore wind farm to the German grid on land.

The DolWin epsilon platform was installed this June. The export cable was installed by the cable supplier Prysmian using Jan De Nul’s vessel Isaac Newton. Prysmian has delivered the connection under an EPCI contract with TenneT, which includes design, procurement, construction and installation.

This content is available after accepting the cookies.

The DolWin5 offshore grid is scheduled to be connected to the German national grid later this year.

The 900 MW offshore grid connection uses extra-high voltage direct current (HVDC) transmission technology. The three-phase alternating current (AC) generated by the Borkum Riffgrund 3 offshore wind farm will be converted into direct current (DC) at DolWin epsilon and transported south to Hamswehrum near the river Ems in East Frisia via the 100-kilometer-long subsea cable.

From Hamswehrum, a 30-kilometer-long onshore cable leads to the converter station in Emden/East where the DC will be converted back into three-phase AC and fed into the extra-high voltage grid on land.

Wind turbine installation at the Borkum Riffgrund 3 offshore wind farm was completed in January this year.

Borkum Riffgrund 3 comprises 83 Siemens Gamesa 11 MW turbines and, with a capacity of 913 MW, is Germany’s largest offshore wind farm.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingGridOffshore WindSubseaBusiness Developments & Projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free