Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›First Malta-Italy interconnector back in service after works on second link demanded shutdown
Cabling

April 2, 2026 · about 5 months ago

First Malta-Italy interconnector back in service after works on second link demanded shutdown

The first interconnector between Italy and Malta has returned to operation after it was shut down due to work on the second interconnector that will connect the two countries. As announced on March 28, the scheduled intervention required the temporary suspension of IC1 to allow for the safe reroutin

1 minutes read
  • LinkedIn
  • X
  • Email
First Malta-Italy interconnector back in service after works on second link demanded shutdown
Source: InterConnect Malta/ Screenshot

The first interconnector between Italy and Malta has returned to operation after it was shut down due to work on the second interconnector that will connect the two countries.

As announced on March 28, the scheduled intervention required the temporary suspension of IC1 to allow for the safe rerouting of control cables in preparation for the foundations of a new 220 kV hybrid switchgear, vital for the integration of IC2, providing the necessary infrastructure to connect spare shunt reactors and enhance the resilience of both interconnectors.

It was reported yesterday, April 1, that IC1 had been re-energized and restored to service following the completion of essential technical interventions at the Ragusa Terminal Station in Sicily.

According to government-owned InterConnect Malta, the works were carried out whilst maintaining full national electricity stability.

Nexans delivered the first Malta-Italy interconnector in 2015. The second one will consist of a new ~122-kilometer-long 225 MW HVAC electrical cable interconnection between the Terna substation at Ragusa, Sicily, and the Enemalta terminal station in Maghtab, to be laid in parallel to the existing link .

Following the completion of the detailed marine route survey carried out by Italy’s Next Geosolutions (NextGeo) , the IC2 interconnector entered the identification and clearance phase which will ensure the seabed along the 99-kilometer subsea cable route is free from potential unexploded ordnance (UXO) and other obstacles.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingInterconnectorsSubseaBusiness & FinanceBusiness Developments & ProjectsInfrastructureOutlook & StrategyProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Noble’s 2013-built drillship scoops up 10-well job in Africa with Tullow Oil
  2. 2North Sea appraisal ops up the oil & gas discoveries’ projected size
  3. 3Vantris Energy rakes in $441.8 million for Petronas and PTTEP offshore works in Malaysia
  4. 4CNOOC keeping Worley busy on its North Sea assets for five more years

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free