Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Marine Energy›CETO wave energy unit’s foundation ready for deployment at BiMEP
Marine Energy

September 22, 2026 · 6 days ago

CETO wave energy unit’s foundation ready for deployment at BiMEP

Carnegie Clean Energy has completed the foundation structures of the scaled CETO wave energy unit in preparation for deployment at Biscay Marine Energy Platform (BiMEP) as part of the ACHIEVE Programme. CETO is a fully submerged, point absorber-type wave energy technology device. A submerged buoy si

1 minutes read
  • LinkedIn
  • X
  • Email
CETO technology
CETO wave energy converter. Source: Carnegie Clean Energy

Carnegie Clean Energy has completed the foundation structures of the scaled CETO wave energy unit in preparation for deployment at Biscay Marine Energy Platform (BiMEP) as part of the ACHIEVE Programme.

CETO is a fully submerged, point absorber-type wave energy technology device. A submerged buoy sits a few meters below the surface and moves with the ocean’s waves. This orbital motion drives a PTO system that converts this motion into electricity.

Carnegie Clean Energy reported today, September 22, that the final preparations had been completed for the foundation, making it ready for deployment of the CETO Buoyant Actuator commencing in October as the first step in ACHIEVE Programme’s staged deployment, commissioning and testing at BiMEP.

Furthermore, the assembly of CETO power take-off (PTO) modules is underway , integrating all power-generating equipment in advance of testing and subsequent integration in the second stage of deployment, while the modular buoyant actuator fabrication is also nearing completion in the Basque Country.

Following completion of the buoyant actuator, it will be transported to the port and prepared for the first stage of deployment. In parallel, the PTO module testing will be undertaken nearby to commission the power-generating assembly in advance of its offshore deployment in the second stage.

The unit will operate at BiMEP for two years, gathering data to validate CETO technology and advance commercialization.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Marine EnergyTidal & Wave EnergyBusiness & FinanceBusiness Developments & ProjectsInnovationOutlook & StrategyProject & TendersTechnology

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Southeast Asian oil field development clears key environmental hurdle to move toward FID
  2. 2‘Major’ oil & gas player awards Shearwater with three-year contract off South America
  3. 3Noble’s 2013-built drillship scoops up 10-well job in Africa with Tullow Oil
  4. 4North Sea appraisal ops up the oil & gas discoveries’ projected size

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free