Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Project & Tenders›Rig provider and other contractors revealed for Timor-Leste's oil field
Project & Tenders

October 15, 2026 · 1 hour ago

Rig provider and other contractors revealed for Timor-Leste's oil field

NS

Nadja Skopljak

Managing Editor

2 minutes read
  • LinkedIn
  • X
  • Email
Hakuryu-5 semi-submersible rig
Hakuryu-5 semi-submersible rig. Source: ENEOS Drilling

Oil & gas exploration player Finder Energy has awarded Japanese ENEOS Drilling a contract to provide a semi-submersible drilling rig for the development of its offshore oil field in Timor-Leste.

ENEOS Drilling's Hakuryu-5 semi-submersible drilling unit will perform the drilling campaign at the Kuda Tasi and Jahal (KTJ) project, including three firm development wells, with options for two additional wells. The Japanese player will also provide the associated equipment and personnel.

The contract is conditional upon receipt of the required joint venture, government and Finder board approvals by December 31, 2026, together with ENEOS parent company and board approvals by November 16, 2026.

The campaign will begin on December 1, 2027, and has an estimated duration of approximately 150 days to drill and complete the wells for production, including running completion assemblies and installation of the wellheads and Christmas Trees ready for hook-up to the Petrojarl I FPSO.

"Securing the Hakuryu-5 is a major milestone for the KTJ Project which brings us a step closer to FID and providing clear visibility on the timing of the development drilling program," said Damon Neaves, Finder Energy CEO. "This is also a strong signal of the progress being made towards delivering Timor-Leste's next offshore oil development."

According to Finder Energy, the two optional drilling slots provide flexibility to accommodate participation by other operators or to undertake exploration or appraisal drilling targeting potential tie-back opportunities within PSC 19-11.

As for other contractors selected for the project, Finder Energy reported that Sumitomo will manufacture, supply and deliver oil country tubular goods (OCTG) including casing, production liner and completion tubing, three Christmas Trees are under fabrication by OneSubsea, and that wellheads have been acquired from another joint venture.

AGR will provide integrated drilling management services to support the planning, management and execution of the development drilling program on behalf of Finder, with Finder retaining overall responsibility as operator, and SLB will supply upper completion equipment for the development wells, including downhole flow-control valves, gauges, chemical-injection equipment, packers, subsurface safety valves, control lines, cables, protectors, splices, contingencies and spares.

The final investment decision (FID) for the project is anticipated by November 30.

Related Articles

Fossil Energy

Southeast Asian oil field development clears key environmental hurdle to move toward FID

2 min read

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Project & TendersFossil EnergyOil & GasSubseaExploration & ProductionContracts & TendersFPSO & VesselsRigs

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Minesto reports 'record' 48-hour service intervention on its tidal power plant
  2. 2Rig provider and other contractors revealed for Timor-Leste's oil field
  3. 3Subsea7 contracts Worley for Northern Lights' key subsea structures
  4. 4Ofgem to launch record tender looking for owner of Hornsea 3 offshore transmission assets

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free