MEO Australia Announces Artemis-1 Progress Report

MEO Australia Limited advises that since the last progress report, the over-pressured zone has been stabilised by circulating 11 ppg mud and an additional 40 metres has been drilled to 2,976m to enable the zone to be isolated behind 9-5/8” casing. As at 05:00 (Perth time) this morning, preparations

1 minutes read

MEO Australia Limited advises that since the last progress report, the over-pressured zone has been stabilised by circulating 11 ppg mud and an additional 40 metres has been drilled to 2,976m to enable the zone to be isolated behind 9-5/8” casing .

As at 05:00 (Perth time) this morning, preparations were underway to run and cement the 9-5/8” casing.

Current expectations are that drilling will resume on Friday 10th December.

Songa Venus semi-submersible drilling rig arrived at the Artemis-1 location at 03:10 hours (Perth time) on Tuesday 23rd November.

[mappress]

Source: MEO Australia, December 8, 2010;

Advertisement

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.