‘Olympus Taurus’ Installs Half of Inter-Array Cables at DanTysk OWF

The Olympus Taurus multipurpose vessel from VSMC has completed the installation of more than half of inter-array cables at DanTysk offshore wind farm.

'Olympus Taurus' Installs More than Half Inter-array Cables at DanTysk OWF

A cable of a 145 mm diameter will transport the electricity from turbines to the offshore substation.

The 80 turbines are organized in eight strings to decrease power losses in the collector system and to achieve greater reliability.

Until now the cable that Olympus Taurus has laid is enough to connect around 40 turbines to the substation.

The DanTysk offshore wind farm, situated west of the island of Sylt and directly on the German-Danish border, will be one of the first large-scale offshore wind farms ever to be built in the German North Sea.

Subsea World News Staff, May 29, 2014