Greece

PGS seismic vessel takes onboard 89 Afghan refugees
Seismic

PGS seismic vessel takes onboard 89 Afghan refugees

PGS’ 3D seismic vessel Ramform Hyperion yesterday took onboard 89 refugees coming from Afghanistan that it had encountered while in transit from Greece to Malta. Ramform Hyperion came across a small sailboat with refugees onboard early on 8 January and made contact with the Italian coastguard who in

about 3 years ago
Owner's engineer services wanted for Mediterranean interconnector
Cabling

Owner’s engineer services wanted for Mediterranean interconnector

EuroAsia Interconnector Limited has issued a tender seeking a provider of owner’s engineer services for the Cyprus – Greece (Crete) part of the link. The role of the owner’s engineer is to provide the specialist technical engineering support required by the owner in the execution of the project thro

about 3 years ago
Seven most read offshore wind Premium articles in 2022
Offshore Wind

Seven most read offshore wind Premium articles in 2022

Updated on 1 February 2023: Our seven most read Premium articles from Offshore Wind were unlocked until 31 January. However, you can still read these and other Premium content by signing up for a yearly or monthly subscription. Or, if you are not already a subscriber, for a free two-week trial. In 2

about 3 years ago
Mediterranean Gas completes ARGO FSRU market test
Clean Fuel

Mediterranean Gas completes ARGO FSRU market test

Greek energy utility company Mediterranean Gas has completed the first phase of the market test for the expression of interest and capacity allocation for the ARGO FSRU terminal in Volos. According to Mediterranean Gas, an expression of interest was submitted by Greek and international companies, wh

about 3 years ago
Hellenic Cables to interconnect two Greek islands
Cabling

Hellenic Cables to interconnect two Greek islands

Hellenic Cables, the cables segment of Cenergy Holdings, has been hired by the Greek Independent Power Transmission Operator (IPTO) to deliver the electrical interconnection between Ionian islands of Kyllini and Zakynthos.

about 3 years ago
Leonardo da Vinci starts installing cables in Greece
Cabling

Leonardo da Vinci starts installing cables in Greece

Prysmian Group’s cable-laying vessel Leonardo da Vinci has commenced the offshore installation campaign of the subsea link that will connect the Greek Crete island and mainland Greece. The Crete-Attica project will comprise a total submarine length of 336 kilometers to be laid at a maximum depth of

about 4 years ago
Hellenic Cables joins in on connecting Greek islands
Cabling

Hellenic Cables joins in on connecting Greek islands

Hellenic Cables has been appointed by the Greek electricity grid operator Independent Power Transmission Operator (IPTO) to deliver the Lavrio-Serifos and Serifos-Milos offshore electrical interconnections. The project that will integrate Milos and Serifos into the continental electricity transmissi

about 4 years ago
Performance Shipping expands its fleet with eco-friendly Aframax tanker
Green Marine

Performance Shipping expands its fleet with eco-friendly Aframax tanker

Greek shipowner Performance Shipping has signed a Memorandum of Understanding (MoU) to purchase an LR2 Aframax oil product tanker vessel built by South Korean shipbuilder Hyundai Heavy Industries (HHI) in 2013.

about 4 years ago
Prysmian cables to link Greek islands
Cabling

Prysmian cables to link Greek islands

Prysmian has secured a circa €150 million contract with the Greek electricity grid operator Independent Power Transmission Operator (IPTO) for an interconnector that will link the islands of Milos, Folegandros and Santorini. The connection is part of Phase D of the Cyclades’ electrical interconnecti

about 4 years ago
DESFA’s new floating storage unit receives first LNG cargo to supplement Greek winter energy demands
Clean Fuel

DESFA’s new floating storage unit receives first LNG cargo to supplement Greek winter energy demands

A floating natural gas storage unit (FSU) installed by Greek gas grid operator DESFA at the LNG terminal of Revithoussa has started operations, increasing the terminal’s storage capacity by 70%. The start of the operation of the FSU was marked by the unloading of the first LNG cargo by MYTILINEOS on

about 4 years ago
Delegation meets to discuss EuroAsia Interconnector
Cabling

Delegation meets to discuss EuroAsia Interconnector

Project developer of the EuroAsia Interconnector and the Cypriot and Israeli delegations have met in Nicosia, Cyprus, to discuss the electricity link that will connect Israel, Cyprus, Greece and continental Europe. A delegation of the Israeli and Cypriot Ministries of Energy, the Israeli and Cypriot

about 4 years ago
Ceremony-in-Cyprus-marks-construction-kick-off-of-EuroAsia-Interconnector
Cabling

Ceremony in Cyprus marks construction start of EuroAsia Interconnector

The EuroAsia Interconnector has entered the construction stage with the launch ceremony held in Nicosia, Cyprus, on 14 October. The EuroAsia interconnector is a Project of Common Interest (PCI) under the 5th Union List comprising a 1,200-kilometer subsea cable from Israel to Crete via Cyprus. As a s

about 4 years ago