Aberdeen-based Hydro Group Plc launches new product, set to be a technological lead in the offshore renewable energy systems market. The group, a global design and manufacturer of underwater cables and connectors for subsea, underwater, topside and onshore applications, invested £300,000 into resear
Since May 12, the Lillgrund offshore wind farm has been standing still. The work to repair the export cable – which transmits the electricity from the wind farm to the substation on land – is underway. “Our focus is to replace the damaged section of the cable as soon as possible and get the producti
Since May 12, the Lillgrund offshore wind farm has been standing still. The work to repair the export cable – which transmits the electricity from the wind farm to the substation on land – is underway. “Our focus is to replace the damaged section of the cable as soon as possible and get the producti
The Carbon Trust, as part of its Offshore Wind Accelerator (OWA), has launched a new competition to fast track the development of new 66kV cables to be used by the offshore wind industry. The goal is to ensure that new 66kV cables are developed in time to be used on Round 3 projects in the […
The load out of DolWin alpha marks the start of a journey that the platform will make to its final offshore destination, the DolWin area in German North Sea. This operation was performed at the Heerema’s Zwijndrecht fabrication yard at the Drechthaven. The following is a video of the load out of Dol
The load out of DolWin alpha marks the start of a journey that the platform will make to its final offshore destination, the DolWin area in German North Sea. This operation was performed at the Heerema’s Zwijndrecht fabrication yard at the Drechthaven. The following is a video of the load out of Dol
National Grid and Statnett confirm plans for further development of the world’s longest subsea interconnector. British energy company National Grid and Statnett, the Norwegian transmission system operator (TSO), have signed a co-operation agreement to continue work on the interconnector to link the
Each time, a cable is installed between wind turbines at an offshore wind farm, time spent offshore can be reduced by approximately three days. A new cable laying concept from DONG Energy points the way to reducing costs. Each time they can move work from the offshore site onshore, they become more
Technip Offshore Wind has started offshore operations on an array cable installation contract for phase 1 of the Borkum Wind Farm development, located 45 kilometers to the North of the German island of Borkum, in the North Sea. This project, awarded by Trianel, is Technip’s first offshore wind, arra
Jee Ltd, a leading subsea engineering and training firm, has just completed a contract with Technip Offshore Wind Ltd for the provision of subsea power cable installation engineering on a new and innovative offshore wind farm project. Jee provided Technip with valuable information about the safest a
Zaratan: 3 Monopiles in 36 Hours (Germany) Following the news that almost 60 monopiles had been completed on 18 March, specialised jack-up vessel Seajacks Zaratan continues installation at a rapid pace at the Meerwind Offshore Park, installing 3 monopiles in just under 1 and a half days. VIDEO: Zara
Zaratan: 3 Monopiles in 36 Hours (Germany) Following the news that almost 60 monopiles had been completed on 18 March, specialised jack-up vessel Seajacks Zaratan continues installation at a rapid pace at the Meerwind Offshore Park, installing 3 monopiles in just under 1 and a half days. VIDEO: Zara
The work for the network connection of the second German offshore wind farm in the Baltic Sea, the EnBW Baltic 2, is in progress. The vessel Aura rinsed the first submarine cable section into the Baltic ground, on Saturday, 20 April 2013, for the connection of Baltic 2. A total of sixty kilometers o
The installation work for the internal transformer platform for Trianel’s Borkum wind farm was successfully completed yesterday. During a two-day mission at the construction site, 45 kilometers off the Borkum’s coast, the heavy lift vessel Oleg Strashnov lifted the 2,400-ton deck onto the substructu