Blue Water Shipping and A2SEA have completed the loading, transportation and installation of three transformer units at the 400MW Horns Rev 3 offshore wind farm in the Danish part of the North Sea. Blue Water loaded the three transformer units onto A2SEA’s installation vessel, Sea Installer, in the
DONG Energy has awarded J. Murphy & Sons Limited (Murphy) the onshore cable installation contract for the 1.2GW Hornsea Project One offshore wind farm. Hornsea Project One, located off the Yorkshire coast, will comprise 174 wind turbines installed across an area of 407sq km, and will be the first of
DONG Energy has awarded J. Murphy & Sons Limited (Murphy) the onshore cable installation contract for the 1.2GW Hornsea Project One offshore wind farm. Hornsea Project One, located off the Yorkshire coast, will comprise 174 wind turbines installed across an area of 407sq km, and will be the first of
EnBW has issued an invitation to tender for inter-array cabling for the Albatros offshore wind project. The tender calls for the provision of turnkey planning and project certification, procurement, manufacturing, delivery and installation of approximately 32 kilometres of inter-array subsea cables,
EnBW has issued an invitation to tender for inter-array cabling for the Albatros offshore wind project. The tender calls for the provision of turnkey planning and project certification, procurement, manufacturing, delivery and installation of approximately 32 kilometres of inter-array subsea cables,
Energy Union Vice-President Maroš Šefčovič and Climate Action and Energy Commissioner Miguel Arias Cañete will attend the Energy Infrastructure Forum tomorrow in Copenhagen, where they will also meet with the Danish Energy Minister Lars Christian Lilleholt. The forum, hosted by the European Commissi
Ofgem has approved a 650km long subsea interconnector between Norway and Scotland, planned to be installed in 2021. On 20 June 2016, Ofgem granted an electricity interconnector licence to Norway-based company NorthConnect KS, authorising it to participate in the operation of the NorthConnect KS inte
During the test phase of the DolWin2 offshore grid connection, a cable component had failed repeatedly and TenneT decided to power off the system and has asked ABB to address the issue. The companies will now investigate whether an individual case or a systemic material error is in question, and the
The export cable at the Burbo Bank Extension offshore wind farm has been pulled in. The cable was floated ashore on pillow floats to a small jack up barge then pulled through the tidal and connected to a winch for the final 760-metre pull through a HDD that had been installed 12 months ago, accordin
The export cable at the Burbo Bank Extension offshore wind farm has been pulled in. The cable was floated ashore on pillow floats to a small jack up barge then pulled through the tidal and connected to a winch for the final 760-metre pull through a HDD that had been installed 12 months ago, accordin
VBMS has completed cable installation and post-lay burial work at Vattenfall’s 288MW Sandbank offshore wind farm, situated in the German Bight. The company installed a total of 76 inter-array cables within approximately two and a half months. VBMS deployed its multipurpose vessels Ndurance and Ndeav
VBMS has completed cable installation and post-lay burial work at Vattenfall’s 288MW Sandbank offshore wind farm, situated in the German Bight. The company installed a total of 76 inter-array cables within approximately two and a half months. VBMS deployed its multipurpose vessels Ndurance and Ndeav
Bard Offshore 1 marked another first for German offshore wind farms after recently generating 3 TWh of electricity since first starting to produce power in 2013. The wind farm has generated 1 TWh of electricity since November 2015, when Ocean Breeze Energy announced the wind farm reaching the 2 TWh
The 219MW Humber Gateway offshore wind farm generated 854,400 MWh of electricity in its first full year of generation, E.ON reports. The wind farm’s 73 turbines moved into full operation in May 2015, and the site was officially opened by Energy Minster Andrea Leadsom MP in September. The figures are