A subsea cable that runs from the Horns Rev 2 offshore wind farm to the onshore grid is out of operation, Energinet.dk reported. After an error occurred on the cable at 01:56 last night, Energinet.dk went to the site to locate the faulty part and will start the repair work if necessary. It is still
Navitus Bay developers have decided not to challenge the decision of the Department for Energy and Climate Change to refuse consent for the offshore wind farm. “We would like to thank the communities on the South Coast and all our stakeholders for their engagement throughout the project. We would al
Navitus Bay developers have decided not to challenge the decision of the Department for Energy and Climate Change to refuse consent for the offshore wind farm. “We would like to thank the communities on the South Coast and all our stakeholders for their engagement throughout the project. We would al
The last of 150 foundations at the Gemini offshore wind farm was installed on 17 October. On 1 July, Van Oord’s installation vessel Aeolus, together with Swire Blue Ocean’s Pacific Osprey, started the installation and completed the work one month earlier than scheduled. On 1 February 2016, both vess
DeepOcean will provide installation and trenching works for DONG Energy’s Walney Extension offshore wind project in the Irish Sea. Offshore works are expected to commence in the first quarter of 2017, subject to DONG Energy taking a final investment decision to proceed with the project. The works wi
The replacement of two sections of the cable that connects the Anholt offshore wind farm to the grid is expected to take place between 26 October and 23 November, depending on weather conditions, Energinet.dk informed. While the work is on, the island of Anholt will be powered from the its own diese
Over 40 items of unexploded ordnance (UXO) from World War II have been safely detonated or removed from the Norfolk coast, having been discovered on the export cable route for DONG Energy’s Race Bank offshore wind farm. During a large scale offshore inspection campaign on the Race Bank site, 41 UXO
The Danish Energy Agency (DEA) and the national Nature Agency have made the environmental impact assessment (EIA) report for Kriegers Flak offshore wind farm available for public consultation. In line with this, Energinet.dk will hold three public meetings. Before the construction of the offshore wi
Donald Trump has taken the fight against the European Offshore Wind Deployment Centre (EOWDC) project to the Supreme Court in London, which held a hearing today. After losing a couple of times in the Scottish courts, the Trump Organization decided to file a lawsuit against the 11-turbine project to
EWE AG and Trianel have set up a joint venture to develop the second stage of the Trianel Windpark Borkum (TWB II) with a capacity of 200MW. Ines Kolmsee, Chief Operating Officer of EWE AG, stated: “EWE brings in its expertise from the development and operation of the first German offshore wind farm
Danish Energy Agency (DEA) reported yesterday that it received eight applications for pre-qualification to participate in the tender for the 600MW Kriegers Flak, Denmark’s largest offshore wind farm. This is the largest number of applicants for a wind farm tender in Danish wind history. DEA said tha
Danish Energy Agency (DEA) reported yesterday that it received eight applications for pre-qualification to participate in the tender for the 600MW Kriegers Flak, Denmark’s largest offshore wind farm. This is the largest number of applicants for a wind farm tender in Danish wind history. DEA said tha
EEW Special Pipe Constructions GmbH received an order from Nobelwind NV to manufacture 50 monopiles and one monopile foundation for the substation for the Nobelwind offshore wind farm (formerly Bligh Bank) in Belgium. The offshore wind farm will have a capacity of 165 MW and is located approx. 47 km
FoundOcean, on behalf of Geosea, has completed the grouting of the XL monopile foundations at DONG Energy’s Gode Wind 1 and 2 offshore wind farm. The wind farm, which is located in the German sector of the North Sea, is the latest wind farm to fix its foundations using the MasterFlow 9500 material f