Dredge idle in Melbourne – $1.5m penalty

The Dutch dredging firm contracted to deepen Melbourne’s shipping channels will reap at least $1.5 million in penalties as the project continues to be delayed. Dredging was due to begin last Friday and is now four days behind schedule as the Port of Melbourne Corporation (PoMC) awaits federal approv

1 minutes read

The Dutch dredging firm contracted to deepen Melbourne’s shipping channels will reap at least $1.5 million in penalties as the project continues to be delayed.

Dredging was due to begin last Friday and is now four days behind schedule as the Port of Melbourne Corporation (PoMC) awaits federal approval of an environmental management plan (EMP).

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.