Ukraine: Works on Ulstein PSV Hull Assembly Running as Scheduled

By the words of production director, Mr. Oleg Bezusiak, work of Zaliv over the Hull YNO. 01298 for Ulstein (PSV) has come to the stage of assembly of the hull. Laying up of the Hull took place in the end of October when first mega-block weighting approximately 145 tons has been loaded into the gravi

1 minutes read

By the words of production director, Mr. Oleg Bezusiak, work of Zaliv over the Hull YNO. 01298 for Ulstein (PSV) has come to the stage of assembly of the hull.

Laying up of the Hull took place in the end of October when first mega-block weighting approximately 145 tons has been loaded into the graving dock. At present moment already four blocks have been loaded onto the Hull with the total weight of approximately 1033 tons.

Such velocity gives the possibility to say that works are in progress without breaks in delivery and the complete assembly of the hull will be finished within November 15.

The delivery of the Hull is planned for middle of January 2013.

[mappress]

Press Release, November 12, 2012

Advertisement

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.