Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Subsea›Nautilus in Solwara 1 Delay as Ship Construction Sits Idle
Subsea

May 1, 2018 · about 8 years ago

Nautilus in Solwara 1 Delay as Ship Construction Sits Idle

Toronto-based underwater mineral exploration company Nautilus Minerals has informed that the construction of its chartered production support vessel has halted pending the resolution of the default situation by MAC Goliath. MAC Goliath, the purchaser of the vessel, had failed to pay the third instal

2 minutes read
  • LinkedIn
  • X
  • Email

Toronto-based underwater mineral exploration company Nautilus Minerals has informed that the construction of its chartered production support vessel has halted pending the resolution of the default situation by MAC Goliath.

MAC Goliath, the purchaser of the vessel, had failed to pay the third installment of the contract price (approximately $18 million plus interest) to Fujian Mawei Shipbuilding.

As reported earlier , if MAC fails to remedy the default, the shipyard may rescind the shipbuilding contract between the shipyard and MAC. In the event that the contract is rescinded, the shipyard has the right to either complete or not complete the vessel and to sell the vessel by private sale either in a complete or incomplete state.

In accordance with the terms of the contract Nautilus Minerals wholly-owned subsidiary has the option to either remedy the default on behalf of MAC and/or replace MAC as a party to the contract by way of a novation or assignment.

Nautilus said it continues discussions with the Shipyard, MAC and third parties with respect to the default and potential remedies, including in regards to one or more third parties assuming responsibility for the completion of the vessel and subsequent charter to the company.

The vessel has been launched by the Shipyard, and remains docked near the shipyard’s facilities in China.

As a result of the delays in securing the remaining project financing and delays in resolving the MAC default situation, the timing for initial production at the Solwara 1 Project is expected to be delayed past Q3 2019.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

SubseaBusiness & FinanceEquipmentOperations & MaintenanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Dolphin Drilling parts ways with 52-year-old rig and forges pact with SPM
  2. 2Fugro's 18-meter USV on survey duty at 'world's longest interconnector'
  3. 3Energy Drilling lines up 30-month job to keep its rig busy through 2030
  4. 4Siem Industries orders two subsea construction vessels from China

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free