Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›DEME looking for replacement installation vessel for Moray East OWF
Offshore Wind

May 5, 2020 · about 6 years ago

DEME looking for replacement installation vessel for Moray East OWF

DEME is currently looking for a replacement vessel for the installation of Moray East jacket foundations, following the crane accident onboard the installation vessel Orion. The company is considering both the vessels in its own fleet and externally to carry out the installation of Moray East jacket

2 minutes read
  • LinkedIn
  • X
  • Email
An archive photo of the Orion installation vessel with the crane onboard
DEME/Archive

DEME is currently looking for a replacement vessel for the installation of Moray East jacket foundations, following the crane accident onboard the installation vessel Orion .

The company is considering both the vessels in its own fleet and externally to carry out the installation of Moray East jackets, first eight of which have now arrived at the Port of Nigg.

”We are doing our utmost to minimise the impact on the project,” a spokesperson for DEME said in an email statement sent to our sister news site OffshoreWIND.biz .

The Orion is scheduled for delivery to DEME in the second half of this month. The vessel was supposed to set sail for the UK to work on the Moray East offshore wind farm shortly after the takeover by DEME.

However, as reported on 2 May, the Liebherr heavy-lift crane installed on the Orion collapsed during a load test in Rostock, Germany, leaving the crane heavily damaged and the vessel with some damage on the deck.

DEME confirmed to OffshoreWIND.biz on 5 May that the first findings pointed to a failure of the crane hook as the cause of the accident.

Further investigations are being undertaken to confirm the cause of the accident, as well as the extent of the damage to both crane and vessel.

On the Moray East offshore wind farm, the Orion was to install 103 jacket foundations, 100 for the project’s wind turbines and three for the offshore substations.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindVessels

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Methanol-ready energy subsea construction vessel arrives in Norway for completion
  2. 2Equinor employs 2009-built Odfjell Drilling rig for additional wells
  3. 3Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection
  4. 4More oil found at permit offshore Gabon

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free