Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Decommissioning›GALLERY: Heerema’s Sleipnir vessel in record-breaking jacket lift for Shell
Decommissioning

August 12, 2020 · about 6 years ago

GALLERY: Heerema’s Sleipnir vessel in record-breaking jacket lift for Shell

Heerema’s giant semi-submersible crane vessel Sleipnir has removed Shell’s 10100 mT Brent Alpha jacket, which was located in the UK North Sea.

2 minutes read
  • LinkedIn
  • X
  • Email
Sleipnir SSCV
Sleipnir SSCV; Source: Heerema

Heerema’s giant semi-submersible crane vessel (SSCV) Sleipnir has removed Shell’s 10100 mT Brent Alpha jacket, which was located in the UK North Sea.

Located 186 km off the northeast coast of the Shetland Islands, the Brent Alpha platform comprised a topsides structure supported by a steel six-legged jacket standing in 140 m of water.

The Brent Alpha topside was removed in a single lift in June with the Pioneering Spirit vessel.

Brent Alpha was the third of four platforms, after Delta (2017) and Bravo (2019), to be decommissioned and removed from the Brent oil and gas field.

According to Heerema’s statement on Wednesday, this single jacket lift breaks Sleipnir’s recent record for lifting the 8100 mT Jotun-B jacket form July.

The Brent Alpha project is Sleipnir’s fourth decommissioning job for this summer.

The vessel will continue to be busy in the North Sea before swapping the largest lifts for one of the smallest with the installation of Dana Petroleum’s P11-Unity Platform later this year.

So far, Sleipnir has removed and transported more than 43900 mT of decommissioned offshore infrastructure for recycling over this summer campaign.

For the Brent Alpha jacket removal, Sleipnir arrived at the Brent field located 186 km northeast of Scotland’s Shetland Islands on 23 July 2020.

It completed the project by offloading the jacket onto the quayside at the AF Miljøbase decommissioning site in Vats, Norway on 11 August 2020.

During the project, Heerema cut jacket legs at 7.3m diameter using a 288” Diamond Wire Cutting Tool developed alongside CUT UK, especially for the Brent Alpha removal – the largest leg diameter to have been cut this way.

Also, during this project, Heerema removed and transported the conductors with the jacket, an entirely new way of decommissioning. The conductors were suspended on a Heerema Fabrication Group built Conductor Hang-off Frame made for this project.

Now that the Brent Alpha jacket has been transported to Vats, it will end its lifecycle by being over 97 per cent recycled.

Heerema’s Decommissioning Director, Jeroen van Oosten , noted that there were quite some technical challenges during this record-breaking lift; such as the cutting of the 3 x 288″ legs of the platform.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DecommissioningFossil EnergyOil & GasSubseaBusiness & FinanceBusiness Developments & ProjectsHeavy liftingInfrastructureOperations & MaintenanceVessels

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1North Sea appraisal ops up the oil & gas discoveries’ projected size
  2. 2Vantris Energy rakes in $441.8 million for Petronas and PTTEP offshore works in Malaysia
  3. 3CNOOC keeping Worley busy on its North Sea assets for five more years
  4. 4Fit-out of NeuConnect’s converter stations in progress

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free