Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Expanding Princess Amalia Harbor’s quay facilities
Dredging

February 22, 2021 · about 5 years ago

Expanding Princess Amalia Harbor’s quay facilities

The Port of Rotterdam Authority has awarded the construction of around 2.4 kilometers of quays and earth-retaining walls in the Princess Amalia Harbor to the HOCHTIEF, Ballast Nedam and Van Oord consortium. The construction of the quays marks the start of the further development of the harbor locate

2 minutes read
  • LinkedIn
  • X
  • Email
Expanding Princess Amalia Harbor’s quay facilities
Van Oord

The Port of Rotterdam Authority has awarded the construction of around 2.4 kilometers of quays and earth-retaining walls in the Princess Amalia Harbor to the HOCHTIEF, Ballast Nedam and Van Oord consortium.

The construction of the quays marks the start of the further development of the harbor located on Maasvlakte II.

The development will increase annual throughput capacity in the port of Rotterdam by four million standard containers (TEU).

“We are paying special attention to reducing emissions during the execution, for instance by using Hydrotreated Vegetable Oil (HVO). HVO fuel has a carbon reduction of 89 percent compared with diesel and has lower emissions of particulates, nitrogen and sulphur,” said Mark van der Hoeven , Director Netherlands at Van Oord.

“By deploying equipment powered by HVO as well as electric construction equipment, we are working fully in line with the Port Authority’s ambitions to significantly reduce harmful emissions.”

Project in brief

The new building work will be on either side of the harbor, which is approximately 2.5 kilometers long. In total, this includes 1,825 meters of deep-sea quay, 160 meters of inland shipping quay and 360 meters of earth-retaining walls.

Barring 725 meters, this means that the entire harbor basin, which went into use in 2015, will be enclosed.

The project also includes the construction of a 160-meter waiting area for general use by inland shipping vessels.

The completion of the first 500 meters of quay wall is expected in late 2022, said Van Oord.

The final part of the project will be completed no more than eighteen months later.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingGreen MarineBusiness Developments & Projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 122-year Cheniere-Petrobras LNG pact expands energy bridge between North and South America
  2. 2Next chapter of Shell’s Canadian LNG project brings Fluor-JGC JV multibillion-dollar award
  3. 3Subsea production systems for Mozambique’s deepwater LNG project ordered from OneSubsea
  4. 4Shell’s platform departs for Trinidad & Tobago’s offshore realm as NGC locks in gas from two upcoming projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free