Ideol-Sets-Up-Partnership-for-Floating-Wind-Mooring-Solutions
Offshore Wind

Ideol sets up partnership for floating wind mooring solutions

Ideol and Bridon-Bekaert Ropes Group (BBRG) have entered a strategic partnership to develop a new synthetic mooring solution for the floating offshore wind market. According to the parties, the goal is to meet the floating offshore wind market’s cost reduction, capacity and lead-time expectations. “

about 6 years ago
Ninian Northern topside ready for decommissioning; Source: Lerwick Port Authority
Decommissioning

Ninian Northern topside set for decommissioning at Lerwick port

The 14,200-tonne Ninian Northern topside has been loaded onto its final resting place – the Dales Voe decommissioning pad at Lerwick Harbour.

about 6 years ago
Scots-Awarding-Half-a-Million-Pounds-for-Offshore-Wind
Offshore Wind

Scots awarding half a million pounds for offshore wind

Crown Estate Scotland is awarding £500,000 for the development of the local offshore wind market. The funds comprise £300,000 for Scottish Offshore Wind Energy Council (SOWEC) projects and £200,000 for environmental research. The awarding of SOWEC funding will be linked to criteria which include ali

about 6 years ago
Boskalis secures first floating wind projec
Offshore Wind

Boskalis secures first floating wind project

Boskalis has won the contract to transport and install five floating wind turbines for the Kincardine floating wind farm in Scotland. For Cobra Wind International Ltd, Boskalis will transport and install the MHI Vestas 9.525 MW floating wind turbines at the site fifteen kilometers off the coast of A

about 6 years ago
An OTM sailing out of Belgium to Moray East site
Grid

Final OTM en route to Moray East Site

A couple of days after its jacket foundation was installed, the third and final offshore transformer module (OTM) has left Belgium and is now on the way to the Moray East site off Scotland. Siemens Energy, which secured a contract to deliver the three OTMs for Moray East in 2018, announced last week

about 6 years ago
Pioneering Spirit bringing the Ninian Northern topside to Lerwick; Image: Rory Gillies/Shetland Flyer Aerial Media Allseas decommissioning
Decommissioning

GALLERY: Pioneering Spirit brings Ninian Northern topside for decommissioning

Allseas’ giant heavy lift vessel Pioneering Spirit has delivered the 14,200 tonne Ninian Northern platform topside to the Lerwick port in Scotland for decommissioning.

about 6 years ago
An archive photo of Seajacks Scylla, the vessel now installing jacket foundations at the Moray East offshore wind farm
Deepwater Installation

Jacket foundation for Moray East OSP1 in place

The jacket foundation for the third offshore transformer module (OTM) for Moray East offshore wind farm has been installed at the site off the Scottish coast. According to the project’s latest Notice of Operations, the jack-up vessel Seajacks Scylla installed the OSP1 jacket on 30 August. Meanwhile,

about 6 years ago
Illustration; Western Isles FPSO; Source: Dana Petroleum
Fossil Energy

Dana Petroleum picks new chief executive officer

Aberdeen-headquartered oil and gas company Dana Petroleum has appointed a new chief executive officer (CEO) of the company.

about 6 years ago
Moray East OSP OTM at Hoboken yard in Belgium
Grid

Third OTM for Moray East offshore wind farm ready to go home

OSP1, the third and final offshore transformer module (OTM) that will be installed at the Moray East offshore wind farm, is ready to leave Belgium this weekend (29 – 30 August). The OTMs, for which Siemens Energy secured a contract in 2018, were fabricated by Smulders and ENGIE Solutions in Hoboken,

about 6 years ago
An offshore wind technician on top of a wind turbine
Offshore Wind

World gets 2.5 GW of offshore wind in first half of 2020

Globally, 2,535 MW of offshore wind was put into operation during the first half of the year, with offshore wind installations reaching 29,839 MW by the end of June 2020, according to World Forum Offshore’s (WFO) H1 2020 Global Offshore Wind Report. The organisation said the figures underline the co

about 6 years ago
Neart-na-Gaoithe-Geotechnical-Borehole-Survey-Set-to-Begin
Offshore Wind

Geotechnical borehole surveys set to begin at Neart na Gaoithe OWF

A geotechnical borehole survey campaign is set to begin at the Neart na Gaoithe (NnG) offshore wind project on 1 September. Geotechnical drilling vessel Ocean Vantage is expected to survey 32 of the planned wind turbine and one of the offshore substation locations. The survey works are expected to l

about 6 years ago
Second Moray East OTM on board a barge starting journey to the UK from Antwerp in Belgium
Grid

Second Moray East OTM platform installed

The second offshore transformer module (OTM) is now at its designated location at the Moray East wind farm site off Scotland, according to the project’s Notice of Operations. OSP2, which was shipped out from Belgium on 30 June, was installed shortly after its jacket foundation and the OSP3 platform