Eight Baltic Sea countries that yesterday agreed to build sevenfold the offshore wind capacity currently installed in the Baltic Sea by 2030 have outlined their joint path to minimising the reliance on Russian fossil fuels. Along with the offshore wind buildout, the leaders of the eight countries wi

Denmark will increase the planned offshore wind capacity at the Bornholm Energy Island from 2 GW to 3 GW and enable the transfer of electricity to the German grid, with two political agreements now in place to make that happen. The Danish Government started exploring the possibility to raise the off

Prysmian Group has developed and tested its first 525 kV extruded submarine full cable system for High Voltage Direct Current (HVDC) applications. The company said that this innovation in cable technology will enable a massive increase of the maximum transmission capacity of bi-pole systems up to mo

Danish engineering company Ramboll and its Dutch counterpart Primo Marine have been awarded contracts for consultancy services on the subsea cable routes for the two energy islands planned to be established in Denmark. The contracts, valued at a total of €828,362 and awarded by the transmission syst

Royal IHC has won a contract by Boskalis for the delivery of an advanced modular cable lay spread (MCLS) that will be used in the offshore wind industry. The cable lay system will be used for the installation of inter-array power cables and associated cable protection systems (CPS). Royal IHC will d

50Hertz, German transmission system operator (TSO) in charge of offshore grid connections in the Baltic Sea, has opened a tender for the planning of the route for the subsea cable of the OST-6-1 grid connection. The OST-6-1 offshore grid project will connect the 927 MW Gennaker offshore wind farm, b

Louis Dreyfus TravOcean (LDTVO) has installed all 80 inter-array cables at the 480 MW Saint-Nazaire, France’s first commercial-scale offshore wind farm. A consortium of LDTVO and Prysmian officially secured a contract for the supply and installation of inter-array cables at the 80-turbine Saint-Naza

Seaway 7 has awarded JDR with a contract to supply 66 kV subsea array cables for the EnBW He Dreiht offshore wind farm in Germany. JDR will supply 100 kilometres of 66 kV array cable that will connect the 64 Vestas 15 MW wind turbines at the 900 MW offshore wind farm in the North […]

Fugro has secured a contract with ScottishPower Renewables to carry out UXO geophysical surveys within the East Anglia Hub offshore wind area in the southern North Sea. The start of the activities is 20 July, with all operations expected to be concluded by 31 October at the site offshore Lowestoft t

Seaway 7 has signed a Letter of Award with Moray Offshore Windfarm (West) Limited to start early works on the Engineering, Procurement, Installation and Commissioning (EPIC) of inter-array grid cables for the Moray West offshore wind farm in Scotland. Seaway 7’s scope is under final negotiation and

Nexans has completed the construction of the new XLPE insulation tower at its subsea cable factory in Halden, Norway. Nexans began the expansion of the Halden factory about two months ago and after 69 days the raising of the tower is completed, the company said. The tower is 152.89 meters tall, whic

Marlinks has won a contract to provide cable health monitoring services for the Arcadis Ost 1 wind farm located offshore Germany in the Baltic Sea. According to Marlinks, Arcadis Ost 1 is situated in an area of the Baltic Sea where challenging seabed conditions are present and a swampy topsoil layer

The extension of SSEN Transmission’s simulation, testing and training centre for high-voltage direct current (HVDC) systems in Cumbernauld has officially opened. Established in 2017, the National HVDC Centre is the first facility of its kind in the UK and uses innovative technology to test the use o

Seaway 7 has won a contract for the transport and installation of inner-array grid cables on an offshore wind farm project in the US. The contract is valued at between $ 50 million and $ 150 million. The scope includes the transport and installation of around 160 kilometres of 66 kV subsea power cab