The Crown Estate has reported an increase in investment in Scotland despite the gross surplus from their operations in Scotland falling. Their profit each year is sent to the Treasury for the benefit of the public as a whole, and they continue to invest in the long-term development of their property
When the Rhode Island Supreme Court issued a ruling earlier this month upholding a long-term contract for the sale of power from Deepwater Wind’s proposed wind farm off Block Island, it was a green light for the company to resume work on the project. As the case dragged on for nearly a year, with th
Right now the installation activities for Walney 2 are booming. Crane barges, jack-up vessels and tugs are working out of ports in the East Irish Sea area, primarily out of the ports of Barrow and Mostyn. On 39 of the 51 monopile positions, a transition piece has already been installed, and the last
The onshore transformer at Cleveleys near Blackpool has been tested and is now ready for energisation. The perimeter fence around the substation is in place and the substation now meets the High voltage rules with restricted access. Inside the substation the harmonic filter compound has been finishe
The onshore transformer at Cleveleys near Blackpool has been tested and is now ready for energisation. The perimeter fence around the substation is in place and the substation now meets the High voltage rules with restricted access. Inside the substation the harmonic filter compound has been finishe
On 29 June 2011, Marine Management Organisation and Natural England conducted a site visit at Walney 2 for inspection of the current Marine Licence. The aim of the visit was to inspect Walney Offshore Windfarms implementation of the marine mammal mitigation during piling of monopiles by Svanen. Nois
The export cable pull for the Walney 2 substation was completed at 04.00 on Sunday 3 July, when the export cable was pulled up to the cable deck of the offshore substation. Here the cable ends are being terminated and the fibre optic cables are currently being jointed. Export cable joint completed T
On Saturday 9 April 2011, the first monopile for Walney 2 was installed, and less than three months later all 51 monopiles have been installed. On Sunday 2 July 2011 the last of the 51 monopiles for Walney 2 was successfully driven into the sea bed, and thus the basic foundation for the 51 turbines
From his office in a converted Victorian schoolhouse, Neil Kermode can see little more than centuries-old stone buildings and narrow streets better suited to horse carts than Land Rovers. Yet Kermode, head of the European Marine Energy Centre in Scotland’s Orkney Islands, will tell you he can also s
From his office in a converted Victorian schoolhouse, Neil Kermode can see little more than centuries-old stone buildings and narrow streets better suited to horse carts than Land Rovers. Yet Kermode, head of the European Marine Energy Centre in Scotland’s Orkney Islands, will tell you he can also s
Wind turbines are getting really big — some with blades as long as a football field — and more powerful, often generating 50 times more electricity than the first generation of wind power machines built in the 1980s. But scientists are also studying how to harness the wind in different ways that cou
Community councillors in Dunbar have been updated on the progress of a proposed £1.2 billion offshore wind farm in the outer Forth estuary. Mainstream Renewable Power plans to start construction on the Neart na Gaoithe (Gaelic for ‘strength of the wind’) wind farm about 30 kilometres north of Tornes
Below the surface of America’s coastal waters could be the energy needed to power your clothes drier and other appliances. Some say the tides have the potential to power about five percent of U.S. households by producing nearly 9 GW of renewable energy. A pilot project to test this potential is in t
The Thanet offshore wind farm is the largest operational wind farm in the world. It consists of 100 turbines each with a 3MW generating capacity. The windfarm is located 11.3 km offshore from Foreness Point, in the North Sea. The WTG’s are interconnected by an offshore 33kV inter array cable network