MHI Vestas Offshore Wind has received an order from DONG Energy for the supply of V164-8.0 MW turbines for the 330MW Walney Extension West project in the UK. The order includes a five-year full-scope service contract with an availability guarantee, ensuring optimised performance of the wind power pl
Assigning operators for four Dogger Bank offshore wind projects is the next major step that needs to be taken so that the projects could enter the pre-construction phase. Forewind, the consortium behind the Dogger Bank development, said that the initial aim will be to assign operators for the two pr
The first monopile foundation was installed at the Nordsee One offshore wind farm site on December 15 – ahead of schedule. GeoSea, which has been contracted to install the monopiles produced by Ambau, will continue the work through the remainder of 2015 and into 2016. The monopiles are being install
The first monopile foundation was installed at the Nordsee One offshore wind farm site on December 15 – ahead of schedule. GeoSea, which has been contracted to install the monopiles produced by Ambau, will continue the work through the remainder of 2015 and into 2016. The monopiles are being install
A fracture in the welding that connects the tower top flange with the tower had caused the breaking of the turbine Number 7 at the Samsø (Paludans Flak) offshore wind farm, Siemens said in a statement. With the fracture developing over time, the tower top flange ultimately separated from the rest of
Balfour Beatty has been awarded a £25 million project by DONG Energy to construct a high voltage onshore substation, as part of the new Hornsea Project One offshore wind farm. Work to construct the new onshore substation is planned to start in January 2016, with Balfour Beatty responsible for the bu
The Samsø offshore wind farm has been put back into operation after an incident in which one of the farm’s 10 turbines broke off and fell into the sea, Siemens confirmed to Offshore WIND. The incident in which the nacelle, hub and blades of the 2.3-MW wind turbine fell into the sea happened at aroun
Siemens will supply five of its SWT-6.0-154 direct drive offshore wind turbines for Statoil’s 30MW Hywind Scotland Project, the world’s largest floating wind project. The turbines will be installed on floating foundations operating in water depths between 90 and 120 meters. For the new Hywind Scotla
A group of Members of the Scottish Parliament (MSPs) have asked SSE to award fabrication work contracts for its Beatrice offshore wind project to the BiFab yards in Fife and Arnish. If work on the jackets does not go to these yards, impact on workers, their families and the local economies they are
The call for tenders for Borssele sites I and II, planned to be launched this month, will be delayed until mid-January 2016. This was said by the Dutch Ministry of Economic Affairs, which explained it will wait for the discussion on the draft bill, called Stroom, in the Dutch Senate before launching
Sweden’s Vattenfall has started dismantling the 10MW Yttre Stengrund offshore wind farm after thirteen years of operating in the waters of Kalmar Sound, the company confirmed to Offshore WIND. Yttre Stengrund consisted of five 2MW NEG Micon turbines. Only 50 of such turbines were ever made. The last
Sweden’s Vattenfall has started dismantling the 10MW Yttre Stengrund offshore wind farm after thirteen years of operating in the waters of Kalmar Sound, the company confirmed to Offshore WIND. Yttre Stengrund consisted of five 2MW NEG Micon turbines. Only 50 of such turbines were ever made. The last
EMS Maritime Offshore (EMO) and WindMW have obtained approval for the site surveillance concept, VENTUSmarine, from the Federal Maritime and Hydrographic Agency of Germany (BSH) and the Waterways and Shipping Board (WSV). EMO offers site surveillance to a pool of windfarms in the German EEZ. All wat
Balfour Beatty has sold 33.3% of its interest in the Greater Gabbard Offshore Transmission (OFTO) project for a consideration of £25.5 million. The investment is being acquired by funds managed by Equitix, an investor and fund manager of core infrastructure assets. The consideration is to be paid in