Danish national transmission system operator Energinet.dk has started works to install a 33-kilometre subsea cable which will connect the offshore substation at the 400MW Horns Rev 3 offshore wind farm to the power grid on land. JD Contractor’s multipurpose offshore installation vessel Sima will ins
Dredger Mimar Sinan and the split hopper barge Tiger have started work at the Tahkoluoto offshore wind farm site. The vessels are working on dredging and excavation for foundations and cable ditches. The underground cable and substation will be installed by the next summer, with foundations and subs
Installation works on the 402MW Dudgeon offshore wind farm are progressing according to plan and the project is halfway to being completed, according to Dudgeon Offshore Windfarm Limited (DOWL). The wind farm’s export cables were laid and the jacket for the offshore substation was installed in May.
Hollandia Offshore B.V. and the Danish transmission system operator, Energinet.dk, signed a contract for the engineering, procurement and commissioning of the Kriegers Flak substations on 31 May. The project comprises two unmanned substations which are due for delivery to the installation site in Ap
Shell Setting Up ‘New Energies’ Unit. Oil & Gas Companies to Cause Clash of Giants in Offshore Wind? Shell has created a new division called New Energies, through which the oil and gas giant will invest in wind energy, along with its hydrogen, biofuels and electrical activities, according to The Gua
Engie Fabricom and Iemants completed the load-out of the topside for the 258MW Burbo Bank Extension offshore wind farm at the ENGIE Fabricom’s Hoboken yard on 30 May. The 1180-tonne topside was placed next to the 985-tonne offshore substation jacket on the pontoon. The jacket was loaded onto the pon
Swedish state-owned energy company Vattenfall is about to start the construction of the 400MW Horns Rev 3 offshore wind farm off the west coast of Denmark, which once commissioned in 2018 will be the largest offshore wind farm in Danish waters. The total investment into the project will be just over
The Big Max cable laying barge will start installing the 20-mile submarine cable which will export the electricity produced by the the first US offshore wind farm, the 30MW Block Island, to the mainland later this week. The National Grid (Sea2Shore) subsea cable will connect Block Island, to Naragan
The Big Max cable laying barge will start installing the 20-mile submarine cable which will export the electricity produced by the the first US offshore wind farm, the 30MW Block Island, to the mainland later this week. The National Grid (Sea2Shore) subsea cable will connect Block Island, to Naragan
E.ON has chosen SGS, a Hamburg-based inspection, verification, testing and certification company, to carry out periodic service inspections at the 302MW Amrumbank West offshore wind farm located some 35 kilometers north of the Heligoland in the North Sea. Under the contract, SGS will perform periodi
A 1,500-tonne steel jacket which will support an offshore substation at the 402MW Dudgeon offshore wind farm has been installed in the seabed some 32 kilometres off Cromer, Norfolk. The jacket structure, built by Sembmarine SLP Ltd, was sunk into the seabed using suction bucket technology for the fi
Canada’s Beothuk Energy has chosen Fugro GeoSurveys to carry out bathymetric and geologic compilation, hydrographic data reprocessing, assessment of stability and seismicity, GIS analyses of seabed morphology, and routing options for the proposed 180MW demonstration offshore wind farm in St George’s
Canada’s Beothuk Energy has chosen Fugro GeoSurveys to carry out bathymetric and geologic compilation, hydrographic data reprocessing, assessment of stability and seismicity, GIS analyses of seabed morphology, and routing options for the proposed 180MW demonstration offshore wind farm in St George’s
DNV GL has won a contract to provide the Canadian offshore wind developer Beothuk Energy with the constraints analysis, wind resource and energy assessment, Levelized Cost of Energy (LCOE) modeling and a preliminary wind farm layout for the 180MW St. George’s Bay project off western Newfoundland and