In just 16 days, during the second visit to the Global Tech I construction site, three more foundations were installed. The installation vessel INNOVATION proved to be extremely reliable in installation of the tripod foundations in 40 meters water depth. Arjen Schampers, Technical Director of Global
After a one-year detailed consideration, a confirmation has been given for EUR 500 million to serve for financing Windreich AG’s MEG 1 project. The Deutsch Bank will team up with other banks to approve additional investments of over EUR 1 billion, therefore, just EUR 100 million will be needed for p
Forewind has announced the project boundaries of the first four offshore wind farm projects to be developed in the Round 3 Dogger Bank Zone. The identification of the boundaries for these four offshore wind farms, two that will connect into the national grid in Yorkshire and two into Teesside, is a
International engineering contractor ODE has extended its overseas growth in renewables with a major contract for a new German windfarm. With a 30-year history in the energy sector, the London-based company is determined to use its extensive UK windfarm background to expand into emerging European an
International engineering contractor ODE has extended its overseas growth in renewables with a major contract for a new German windfarm. With a 30-year history in the energy sector, the London-based company is determined to use its extensive UK windfarm background to expand into emerging European an
Osiris Marine Services announce successful completion of diving works on the Lincs Offshore Wind Farm. Supporting offshore foundations market leader MT Højgaard with Diving, ROV, Confined space and tower climbing services continuously for 18 months, Osiris Marine Services played a significant role i
DONG Energy, E.ON and Masdar today announced that the first power had been produced at the London Array Offshore Wind Farm. The 630MW scheme, located in the Thames Estuary, will be the world’s largest offshore wind farm. The development has been under construction since March 2011 and 152 of the 175
A proposal for Phase 2 of the London Array offshore wind farm has been submitted to the Department of Energy Climate Change (DECC) and the Marine Management Organisation (MMO). The developers have reduced the initially proposed extension from 370MW to 240MW, after the surveys had been conducted by N
Six days after the final foundation was installed at London Array the project has achieved another milestone – all array cables have now been installed at the offshore site. The installation of the last array cable was completed on Thursday 25th October by the The Normand Flower. 187 cables have bee
Six days after the final foundation was installed at London Array the project has achieved another milestone – all array cables have now been installed at the offshore site. The installation of the last array cable was completed on Thursday 25th October by the The Normand Flower. 187 cables have bee
Seagreen has submitted applications to the Scottish Government for consent to build and operate two 525 Megawatt (MW) offshore wind farms in Phase 1 of the Firth of Forth Offshore Wind Zone. The applications were formally submitted to Marine Scotland, the Scottish Government directorate responsible
Development of the German Borkum Riffgrund 2 offshore wind farm has been suspended by DONG Energy, due to grid connection issues associated with the grid operator TenneT TSO. TenneT has not provided a firm date for laying the offshore cables, DONG Energy says. On the other hand, the grid operator ex
At midday on Friday 19th October the final transition piece was installed at London Array – marking the completion of the installation of all of the project’s 177 foundations. Richard Rigg, Project Director at London Array said: “The installation of the final foundation at London Array is a signific
Vattenfall and Siemens have signed a contract for the supply and installation of 80 wind turbines for the Sandbank offshore wind farm. Each of the turbines has a nominal capacity of 3.6 megawatts (MW). Construction of the Vattenfall Sandbank project, located 90 kilometres west of the island of Sylt,