Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Clean Fuel›Sempra files request for Port Arthur LNG expansion
Clean Fuel

June 18, 2019 · about 7 years ago

Sempra files request for Port Arthur LNG expansion

U.S. energy company and LNG operator Sempra Energy has filed a request with the Federal Energy Regulatory Commission (FERC) to start the pre-filing review process of the Port Arthur LNG expansion process.

1 minutes read
  • LinkedIn
  • X
  • Email

U.S. energy company and LNG operator Sempra Energy has filed a request with the Federal Energy Regulatory Commission (FERC) to start the pre-filing review process of the Port Arthur LNG expansion process.

The expansion project will be located at the site of the recently approved Port Arthur liquefaction project near Port Arthur, Texas, adding additional liquefaction capacity to the facility, Sempra said in its filing.

The project would add two liquefaction trains which will be located adjacent to Trains 1 and 2 in the base project. LNG produced from Trains 3 and 4 will be stored and exported using storage tanks and marine facilities approved as part of the base project.

The expansion project will increase LNG production capacity from 13.5 million metric tons per annum (mtpa) in aggregate from Trains 1 and 2 to approximately 27.0 mtpa.

The expansion project facilities will be located wholly within property certificated for the base project.

Sempra proposes to file its formal application for the proposed expansion project in January 2020, approximately six months from the expected date of commencement of the pre-filing review process for the expansion project.

In that application, Sempra will request that the commission issue authorization for the siting, construction, and operation of the expansion project by no later than January 2021. Sempra anticipates requesting authorization to begin construction in March 2022.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelVessels

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Fatal rig incident: Search still underway for two missing workers off Gabon
  2. 2Planned wave energy project in India takes step forward
  3. 3CO2 storage appraisal campaign in UK North Sea yields positive results
  4. 4MOL and Deutsche ReGas shake hands on FSRU for German LNG terminal

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free