Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Clean Fuel›Chinese shipyard completes FPSO for BP’s Greater Tortue Ahmeyim LNG project
Clean Fuel

September 13, 2022 · about 4 years ago

Chinese shipyard completes FPSO for BP’s Greater Tortue Ahmeyim LNG project

Chinese shipyard COSCO has completed the construction of an FPSO vessel for BP’s Greater Tortue Ahmeyim project in Mauritania and Senegal.

2 minutes read
  • LinkedIn
  • X
  • Email
BP's Tortue FPSO
BP’s Tortue FPSO; Photo courtesy of COSCO

Chinese shipyard COSCO Shipping Heavy Industry has completed the construction of a floating production storage and offloading (FPSO) vessel for BP’s Greater Tortue Ahmeyim (GTA) LNG project in Mauritania and Senegal.

The completion ceremony for BP’s Tortue FPSO was held at the COSCO yard in Qidong, China last week.

This was announced by COSCO in a statement last week and also confirmed by Technip Energies in an update shared via its social media channels this week.

This content is available after accepting the cookies.

Last week, the Completion Ceremony of @bp ’s Tortue floating production storage and offloading unit (FPSO) was held at the COSCO yard in Qidong, China. Congratulations to everyone involved for accomplishing this project! ? pic.twitter.com/dMYK1qH07i

The GTA project will produce gas from an ultra-deepwater subsea system and mid-water FPSO vessel, which will process the gas, removing heavier hydrocarbon components. The gas will then be transferred to a floating liquefied natural gas (FLNG) facility at a nearshore hub located on the Mauritania and Senegal maritime border.

According to COSCO, the completion ceremony for the N999 Tortue FPSO was held last Friday in the presence of executives from BP, Technip Energies, and others. The vessel is 70 meters long, 54 meters wide, and 31.5 meters deep. The designed service life is 30 years and the oil storage capacity is not less than 1.44 million barrels. The living quarters can accommodate 140 people.

The construction started in May 2019 and it included the design, procurement, construction and commissioning (EPCC) of the main hull and living quarters and the construction and integration of all topside modules.

The key function of the FPSO is to remove water, condensate and reduce impurities in the gas stream before exporting processed gas to the FLNG facility and domestic gas off-take.

As recently reported, the GTA project is on track to achieve the first gas in 3Q 2023 despite FPSO delays. The sailaway date was previously expected to be the end of the third quarter but was later moved to be in the fourth quarter. The first LNG is expected at the end of 2023.

Related Articles

Clean Fuel

First gas from Greater Tortue Ahmeyim on target despite FPSO delay

3 min read

The initial phase of the Greater Tortue Ahmeyim project is expected to deliver approximately 2.5 mmtpa of natural gas. The partnership is also evaluating potential expansion up to 10 mmtpa in subsequent phases.

Phase 2 of the Greater Tortue Ahmeyim LNG project continues to progress and the partnership is working with host governments to evaluate the optimal solution to best utilize the infrastructure associated with Phase 1 of the project. A development decision is planned for the end of the third quarter.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelFossil EnergyFPSO & VesselsGreen MarineLNGOil & GasShipbuildingBusiness & FinanceBusiness Developments & ProjectsProject & TendersVessels

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Black Sea mega-project narrows first gas window to early 2027 with work in final execution stage
  2. 2New JV set up in Nigeria for work with TotalEnergies and other oil & gas majors
  3. 3Subsea Micropiles to invest £5 million in expanding manufacturing, offshore ops at Scottish port
  4. 4Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free