Geotechnical survey work will soon commence along the North Falls export cable route and wind turbine array area in the southern North Sea. Mobilisation will commence on August 3, with the survey lasting approximately two months. The planned survey is expected to conclude no later than September 30,

TGS has completed an ultra-high-resolution 3D (UHR3D) seismic survey for the Green Volt floating offshore wind farm in Scotland, developed by a consortium of Flotation Energy and Vårgrønn. According to TGS, the record-breaking survey integrated Multibeam Echo Sounder (MBES), Sub-bottom Profiler (SBP