Since the first monopile was installed at 19.00hrs on New Year’s Eve, periods of good weather have been used to install foundations. On 1 February 2012, Svanen had erected 14 monopiles. Even though the January weather has been rough, it has been good for foundation installation. Since 27 December, t
State officials are urging the government to help businesses along the East coast take advantage of renewable energy boom. Suffolk MP has invited the government to boost local businesses in that area. Waveney MP stated in the parliament that East Anglia Array Wind Farm offers great opportunity for d
RWE NPower Renewables has changed their plans for connecting a 1,2 GW wind farm to the grid. They initially planned to bring power to the grid trough a 50 mile network of pylons across East Lindsey. The National Grid gave the company an offer to connect the wind farm to the existing electricity tran
Windreich AG has reached a new milestone for the construction of the ‘MEG 1’ offshore wind farm substation. The order for the 400 MW substation is worth tens of millions of euros. Consortium made up of Alstom Grid GmbH and SIAG Schaaf Industrie AG was commissioned for this job. The contract includes
TenneT Offshore GmbH eyes subsea cable installation contractor. The contractor will be in charge of establishing a grid connection between an onshore transformer substation and one or several offshore Wind farms located in the offshore wind farm cluster BorWin on the North Sea. The services include
The first load of totally 70,000 tonnes of armour stones for scour protection has arrived at the Walney construction site. The stones are supplied from the Stainton Quarry and will be used to armour the turbine foundations for scour protection. The stones will be placed in a radius of 15 metres arou
The progress on Walney 2 has been dramatically reduced due to windy weather conditions for the last couple of weeks. Heavy winds and high waves have paused the commissioning activities at Walney 2, making it impossible to access the turbines. When the wave height exceeds certain limits, all personne
The progress on Walney 2 has been dramatically reduced due to windy weather conditions for the last couple of weeks. Heavy winds and high waves have paused the commissioning activities at Walney 2, making it impossible to access the turbines. When the wave height exceeds certain limits, all personne
The establishment of the future operation and maintenance facilities has now come so far that flag and garland could be hoisted on the communication tower to mark the roofing ceremony. Approx 30 workmen, representatives from the harbour, consultants and DONG Energy’s project group were present. Thom
The establishment of the future operation and maintenance facilities has now come so far that flag and garland could be hoisted on the communication tower to mark the roofing ceremony. Approx 30 workmen, representatives from the harbour, consultants and DONG Energy’s project group were present. Thom
The London Array consortium, Abu Dhabi’s Masdar, E.ON, Dong Energy on Monday announced that work is under way at the world’s largest offshor… (wam) [mappress] Source: wam, November 01, 2011
The London Array consortium, Abu Dhabi’s Masdar, E.ON, Dong Energy on Monday announced that work is under way at the world’s largest offshor… (wam) [mappress] Source: wam, November 01, 2011
The innovative elastometric spring bearings designed to improve the vertical load carrying capacity of the wind turbines of the Sheringham Shoal Offshore Wind Farm, have now been installed on each of the 90 foundations at the site, 20 kilometres off the coast of the Norfolk in the UK. Trelleborg Off
The innovative elastometric spring bearings designed to improve the vertical load carrying capacity of the wind turbines of the Sheringham Shoal Offshore Wind Farm, have now been installed on each of the 90 foundations at the site, 20 kilometres off the coast of the Norfolk in the UK. Trelleborg Off