Jan De Nul has repaired TenneT’s AC108 cable connecting the Trianel Borkum offshore substation with Tennet’s DolWin alpha converter station in the German North Sea. The repair job is part of the Service Level Agreement for cable repairs that Jan De Nul and TenneT entered into in 2019. TenneT engaged

NKT has reported a revenue of €296 million in the first quarter of 2021, a 21% organic growth from the €240 million in the same quarter of 2020, with positive growth from all of the company’s three business lines. Operational EBITDA increased for all the business lines and almost tripled from €10.2

Partners Group has become a 100% shareholder in the Greenlink electricity interconnector between Ireland and Great Britain. Partners Group has acquired a 51% stake in Greenlink from Element Power, meaning that it now entirely owns the interconnector on behalf of its clients. Greenlink will use a sub

Ningbo Orient Cable (NBO) has delivered the 33 kV subsea cable for the SSEN Skye-Harris cable replacement project in the UK. NBO completed the production of the 38 kilometers of 33 kV submarine cable after four months of work and loaded it onto the transportation vessel. The cable will now be transp

Oceanteam has secured a contract for the provision of a cable transport spread for a project in the German Baltic area.

IGI Poseidon has selected the contractors for the environmental and social impact assessment (ESIA) and relevant support services related to the offshore and onshore sections of the EastMed pipeline project. ERM Italia will carry out the ESIA and implementation of activities to obtain authorization

Sumitomo Electric Industries has won a contract to supply new 132 kV offshore export cable for the Gwynt y Môr offshore wind project in the UK. The contract award comes a few months after Ofgem ruled in favor of Gwynt y Môr OFTO plc which had filed an Exceptional Event claim for the project’s export

Boskalis has reported a 10 per cent increase in the order book of its Offshore Energy division in the first quarter of the year (compared to the end of 2020), with around 50 per cent of new orders coming from the offshore wind sector. The first quarter at the company’s Offshore Energy division proce

Norwegian seismic company TGS has acquired 4C Offshore, a marketing intelligence and consultancy firm dedicated to the offshore wind sector. The acquisition is TGS’ first after the launch of its New Energy Solutions business earlier this year, established to pursue opportunities related to the energ

NKT is investing more than €150 million in the expansion of its high-voltage power cable production sites and logistics to execute on a record high order backlog. The investment program will see a new high-voltage power cable test center in Cologne, Germany, and the construction of a new extrusion t

Polish GAZ-SYSTEM is carrying out final preparations to begin laying the offshore gas pipeline for the Baltic Pipe project in the Baltic Sea. Drilling of a tunnel for the gas pipeline began in April on the Polish coast, with similar work set to start soon in Denmark, GAZ-SYSTEM said. Allseas will wo

Nexans’ new cable-laying vessel (CLV) Nexans Aurora has commenced its sea trials off the Norwegian coast. Nexans Aurora began the yard sea trial on 3 May and continued with the technical sea trial on 5 May. Ulstein Verft said that the sea trial will continue for a few more days, after which the yard

Helix Robotics Solutions has completed its second trenching campaign of the inter-array cables at the Moray East offshore wind project in Scotland. The work was carried out by construction support vessel Grand Canyon III at the project site located some 22 kilometers off the Aberdeenshire coast. All

Rotech Subsea has completed cable de-burial and post-lay trenching works at an undisclosed offshore wind farm in the British part of the North Sea. Rotech carried out the work on multiple sections of the wind farm. The company did not reveal the name of the client but did state that it is an offshor