Cable laying and burial underway at Viking Link UK landfall
Cable laying and burial works are currently underway at the Viking Link landfall in Lincolnshire, UK. The work covers the first campaign of 51 kilometers starting from the UK landfall at Boygrift. Prysmian PowerLink began the cable laying works on 10 May using Cable Enterprise, with work expected to

Parkwind orders Arcadis Ost 1 inter-array cables at JDR
Belgian offshore wind developer Parkwind has awarded JDR with a contract to supply, test, and terminate 33kV subsea cables for the Arcadis Ost 1 offshore wind farm in Germany. The UK-based JDR will supply the 45 kilometres of 33kV array cable that will connect the wind farm’s 27 MHI Vestas V174-9.5M

Nexans holds naming ceremony for CLV Aurora
Nexans and Ulstein Verft have held the naming ceremony for the newbuild DP3 cable laying vessel (CLV) Nexans Aurora. Despite the Covid-19 pandemic, the project progress has been steady and the vessel was delivered on time on 31 May, three years after the signing of the shipbuilding contract, Ulstein

CLV Leonardo da Vinci sets sail
Prysmian’s new cable laying vessel (CLV) Leonardo da Vinci has completed its first trip to open sea and is ready to begin sea trials. After completing the last outfitting phases, Leonardo da Vinci will undergo sea trials for approximately two weeks and will run three turns of tests. After draught re

Intertek and NIRAS join North Sea Energy Island roster
Energinet has selected Intertek to undertake constraints analysis, consenting advice, and cable route and landfall assessments for the North Sea Energy Island offshore Denmark. The project will include 3 GW of offshore wind farm assets, an energy hub on an artificial island 80 kilometres offshore to

AqualisBraemar LOC gets to work on DolWin5
London-based consultancy AqualisBraemar LOC has secured a contract to provide marine warranty services for the export cable installation of the DolWin5 offshore grid connection project in Germany. The scope of work covers all marine transportation and installation operations relating to the laying o

DLM’s subsea cable holdback tensioner debuts on NKT Victoria
UK-based Dynamic Load Monitoring (DLM) has unveiled a new device for measuring tension and creating holdback force on a single piece of subsea cable. The Saddleback Holdback Tensioner (SB-HBT), which combines the Saddleback product with an additional Hold Back Tension element, is being primarily use

Baltic Pipe needs new environmental permit, process could take up to 8 months
Energinet and the Danish Environmental Protection Agency must make a new environmental impact assessment for the Baltic Pipe project, a process which could take up to 8 months of work, a spokesperson from the agency told Offshore Energy. To remind, the Danish Environmental and Food Appeals Board rul

Russia completes first Nord Stream 2 line
Russia has finished laying the first line of the Nord Stream 2 gas pipeline to Germany, Reuters reported President Vladimir Putin as saying at an economic forum on Friday, 4 June. Nord Stream 2 comprises two parallel 48-inch lines, approximately 1,200 kilometers long, each starting southwest of St.

50Hertz searching for Ostwind 3 cable supplier
German offshore transmission system operator (TSO) 50Hertz has issued a tender seeking a provider of the 220 kV submarine and onshore cable system for the Ostwind 3 grid connection. The selected party will be in charge of the design, engineering, construction, installation, handling and commissionin

Equinor stays with MMT on Beacon Wind
Equinor has selected Sweden’s MMT to carry out the 2021 export cable route surveys for the Beacon Wind wind farm offshore Massachusetts, U.S. The project is led by MMT’s team based in Providence – MMT US Inc. Having commenced in April to complete in July, MMT, the Ocean Infinity company, is conducti

Danes repeal Baltic Pipe environmental permit
The Danish Environmental and Food Appeals Board has ruled to repeal the permit for the onshore part of the Baltic Pipe gas pipeline, which the Danish Environmental Protection Agency granted back in July 2019. According to the appeals board, the permit from the Environmental Protection Agency did not

Installation work about to start on Scotland’s new offshore wind farm
Offshore installation work is set to start this month on a new offshore wind farm to be built off the Scottish coast, for which one of Saipem’s crane vessels and Prysmian’s cable laying vessels will soon mobilise. The DP2 heavy lift vessel S3000 is currently in the Port of Schiedam and will be mobil

Cable connection needed for German offshore platform
Transmission system operator TenneT has issued a notice for a turnkey contract covering the cable system needed to connect the BorWin6 offshore platform to the German grid. With the 930 MW BorWin6 project, TenneT is planning a direct current connection in the North Sea Cluster 7. Scheduled to be com