EstLink 2, the electricity transmission link between Finland and Estonia that was damaged at the end of 2024, is set to return to commercial use on June 25, earlier than planned. Finnish transmission system operator (TSO) Fingrid reported to the authorities on December 25, 2024, the failure of Estli

NKT, using its vessel NKT Victoria, is scheduled to start installing the export cable for the 1.4 GW East Anglia Three offshore wind farm in the UK this month. The vessel is expected to mobilize from the port of Karlskrona in Sweden on June 14 and work on the East Anglia Three site 24/7, conducting