Australia: Santos GLNG hits full operation at Roma East project

Santos GLNG’s $750 million Roma East project has marked a milestone, with the natural gas compression facility officially handed over to the operations team.

Image courtesy of Santos

First gas from the Roma East field flowed in February this year and with commissioning now safely completed, the plant is fully operational, Australian LNG player Santos said in a statement.

The Roma East project involves bringing 480 wells online, including drilling about 430 new wells, connecting existing appraisal wells, and drilling pre-development wells in the surrounding areas.

The project also includes about 420 kilometers of water, gas gathering and other pipelines, 120 TJ per day of additional compression, 670 kilometers of power lines, 25 kilometers of fiber optic cables and a new water-handling facility for irrigation.

Santos vice president CSG Developments, Rob Simpson said, “the compression facility is now taking gas from the 200 new wells which have been brought online since the start of construction.”

He added that the production from Roma has been ramping up and is now about 118 TJ.

Construction on the Roma East project will continue until mid-2020 as the remaining wells are drilled and connected.

When completed, Santos GLNG, a joint venture between Santos, Petronas, Total and Kogas, expects the project will deliver around 50 PJ of additional gas production each year.

Santos has been supplying gas to homes in the region for more than 50 years and, since 2011, Santos and our GLNG partners have invested almost $20 billion in regional Queensland.