Cheniere’s Sabine Pass LNG export project moves ahead

Houston-based LNG player Cheniere filed construction activities report with FERC for its Sabine Pass LNG export terminal in Cameron Parish, Louisiana. 

The report covers activities of the Stage 1 (Trains 1 and 2) and Stage 2 (Trains 3 and 4) projects during the month of November.

According to the filing, Stage 1 Engineering and Procurement are 100% complete, Subcontract and direct hire Construction work are 52.8% and 53.4% complete, respectively. Stage 1 overall project completion is 79% against the plan of 80.2%.

Stage 2 Engineering is now 92.9% complete, Procurement is 72.6%, and Subcontract and direct hire Construction work are 31.2% and 13.6% complete, respectively. Overall project completion for Stage 2 is 49.8% against the plan of 50.0%.

Cheniere informed that construction is on track for the set completion targets for Train 1 and Train two as February 2016 and June 216 respectively. Trains 3 and 4 Substantial Completion Dates are April 2017 and August 2017.

[mappress mapid=”16402″]

LNG World News Staff; Image: Cheniere