NKT Victoria Starts Johan Sverdrup Power Cable Installation

Statoil has informed that the laying of the cable supplying Johan Sverdrup with power from shore has started.

On Wednesday the cable laying vessel NKT Victoria began laying the cables that will supply the Johan Sverdrup field with power from shore.

The starting point was the Johan Sverdrup converter station at Haugsneset near Kårstø, and by the end of May the vessel will have laid nearly 200 kilometers of power cables out to the field in the North Sea, the company said.

We are now laying the very lifeline of the Johan Sverdrup field, which will supply the field with power from shore for more than 50 years,” said Trond Bokn, senior vice president for Johan Sverdrup.

The power cables will help make Johan Sverdrup one of the most carbon-efficient oil and gas fields in the world.

Estimated at just 0.5 kg of CO2 per barrel, the emissions from Johan Sverdrup are about 20 times lower than the average on the Norwegian continental shelf, and 30 times lower than the international average.

“The world is facing considerable challenges ensuring access to enough energy while doing so in a more climate-friendly way. Here Johan Sverdrup will play an important role: over the next 50 years, the field’s considerable reserves will be used to produce significant amounts of energy with low CO2 emissions,” Bokn said.

The CO2 emissions avoided as a result of Johan Sverdrup using power from shore add up to more than 400,000 tonnes of C02 per year, equivalent to the emissions of some 200,000 cars each year.

Several additional measures have been implemented to further reduce emissions during the Johan Sverdrup development. The cable-laying vessel NKT Victoria was designed to be supplied with power from shore while in harbour.

The mobile accommodation vessel ‘Haven’, in use at the field from June onwards, has also been modified to utilize power from shore while in service at the Johan Sverdrup field.

We’ve worked systematically to take advantage of the opportunities which the power from shore solution has given us. As a result, I believe we’ve been able to reduce the carbon emissions from the field to the minimum,” said Geir Bjaanes, responsible for subsea, power and pipelines for the Johan Sverdrup project.

Before we get to that stage, however, we need to stay focused on the hectic installation period ahead of us. For the next three weeks or so we will be laying almost 10 kilometres of cables every single day. We have spent much time together with NKT preparing for this, but this will put our skills to the real test, our number one priority being safety and ensuring high quality in execution,” added Bjaanes.

After the cables reach the Johan Sverdrup field at the end of May, the next step will be to pull the cables in to the riser platform, where the converter station for the first phase of the development is located.

Then the cables will be connected, before preparations and testing of the system start. And in the autumn of 2018, the Johan Sverdrup field should be ready to be powered with electricity from shore.

After the start-up of the second phase of the development in 2022, the Johan Sverdrup field will also enable power from shore to reach the remaining fields on the Utsira High – Edvard Grieg, Gina Krog and Ivar Aasen.