Sea Challenger Loads Final Dudgeon Turbine Parts in Hull
A2SEA’s wind turbine installation vessel Sea Challenger has loaded the final set of wind turbine components for the 402MW Dudgeon offshore wind farm project at the Port of Hull.
In total, the vessel made 17 runs between the load out port in Hull and the installation site some 32 kilometres off North Norfolk to install all of the wind farm’s 67 Siemens 6MW turbines. The first turbines were installed at the site in early January 2017.
Sea Challenger had also served as an accommodation vessel on the project from September 2016 to the end of the year.
The Dudgeon offshore wind farm is a GBP 1.5 billion project being jointly developed by Statoil, Masdar and Statkraft, expected to be fully commissioned by late 2017.
Statoil is developing the Dudgeon offshore wind farm and will continue as its operator.
List of related news articles
-
Posted: 22 hours ago
Triton Knoll enters wind turbine installation phase
Cadeler’s wind farm installation vessel Wind Osprey has arrived at the Triton Knoll wind farm ...
Posted: 22 hours ago -
Posted: 28 days ago
All foundations in at world’s largest freshwater wind farm
Van Oord has installed all of the 89 foundations at the Windpark Fryslân nearshore wind farm in the ...
Posted: 28 days ago -
Posted: 2 days ago
New Jersey OWF to feature GE Haliade-X wind turbines
GE Renewable Energy has signed supply and service contracts for the 1.1 GW Ocean Wind offshore wind ...
Posted: 2 days ago -
Posted: 8 days ago
Bold Tern loads first Moray East turbine hardware
Fred. Olsen Windcarrier’s jack-up Bold Tern is on her way to install the first wind turbines a...
Posted: 8 days ago