Bilfinger Nets Race Bank Foundations Order

Bilfinger Mars Offshore has won an order for the production of 91 steel foundations for the  North Sea wind park.

The wind park, located 28 kilometers from the United Kingdom’s east coast, will have an output of about 580 MW and will provide 400,000 households with electricity. The client is Danish energy company Dong Energy A/S.

For Bilfinger Mars Offshore, the order is the starting signal for the production of offshore foundations at the new production site in the Polish city of Szczecin, the company said.

We will begin with the work as soon as the plant is officially opened in October 2015 and will complete production of the steel foundations by the end of the coming year”, says the responsible Member of the Bilfinger Executive Board, Joachim Enenkel.