Burbo Bank Extension Progresses with Wind in Its Sails

DONG Energy’s Burbo Bank Extension offshore wind farm project remains on track having met a key contractual milestone.

The project has demonstrated that 10 per cent of total project expenditure has now been spent, a fundamental contractual requirement which had to be met for the milestone to be delivered. This is one of the requirements the project must achieve to qualify for its investment contracts. Burbo Bank Extension was one of five UK offshore wind farms awarded an early contract CFD in April 2014 under the Government’s Final Investment Decision (FID) Enabling for Renewables process.

The CFD will guarantee that the projects will receive a fixed price per megawatt hour of electricity produced during its first 15 years of operation. The CFD is the new mechanism developed by Government for funding low carbon generation. After this the wind farm will receive the prevailing market price. Burbo Bank Extension is the first project in the UK to comply with the CFD milestone.

Expected to be commissioned in 2017, the 258 megawatt wind farm in Liverpool Bay will be able to supply the electricity needs of around 180,000 UK homes. Having received development consent in September last year, the wind farm will consist of 32 MHI Vestas Offshore Wind 8 MW wind turbines.

Klaus Skoust Møller, DONG Energy’ s senior programme director for Burbo Bank Extension said:

“I am delighted that we have achieved this milestone. Getting the submission together was a real team effort with over 300 documents produced to ensure we met the requirements of the Government’s CFD delivery body, the Low Carbon Contracts Company, who helped us by maintaining an open dialogue throughout the process.”

He added: “The milestone is a significant achievement for the project which demonstrates our commitment to deliver Burbo Bank Extension to time and cost. It also confirms DONG Energy wider commitment to offshore wind in the UK. We have already placed a number of important contracts and the pace of the project is increasing month on month. Work has been ongoing for some time now onshore in St. Asaph and this is progressing well.

“The Burbo Bank Extension will be using the world’s largest available offshore wind turbines and, when commissioned, the wind farm will represent another significant step towards reducing cost of electricity on future projects.”

Image: dong energy