Dredge idle in Melbourne – $1.5m penalty

The Dutch dredging firm contracted to deepen Melbourne’s shipping channels will reap at least $1.5 million in penalties as the project continues to be delayed.

Dredging was due to begin last Friday and is now four days behind schedule as the Port of Melbourne Corporation (PoMC) awaits federal approval of an environmental management plan (EMP).