Lundin Petroleum: Alvheim FPSO successfully hooked-up on Alvheim Field

The Alvheim FPSO left the port in Haugesund on the 16 February for final commissioning and testing in the Amoyfjord. Due to adverse weather conditions the sailaway to the final location on the Alvheim field was delayed.

The Alvheim FPSO was moved from the Amoyfjord on the 25 March to the Alvheim Field and was successfully hooked-up to the buoy on the 27 March according to plan. The plan forward is to continue ordinary commissioning and production start-up preparations. First oil from the Alvheim Field is expected by the end of April.