MEO Australia Provides Update on Blackwood-2 Drilling

MEO Australia Provides Update on Blackwood-2 Drilling

MEO Australia said that on Friday the Ensco 104 jack up drilling rig was preparing to commence the wireline logging program having drilled to total depth at 3,425mMDRT.

Progress Summary

Progress since last report:

  • Drilled 216mm (8½”) hole from 3,150mMDRT to 3,226mMDRT
  • Cut core from 3,226m to 3,283mMDRT (recovered 60m)
  • Drilled 216mm (8½”) hole from 3,283mMDRT to 3,425mMDRT (Total Depth)
  • Prepared to commence wireline logging program

Present Operation:

  • Preparing to conduct wireline logging program

Outlook:

  • Production test (if warranted)
  • Plug and abandon well