Morro Bay Dredging Progresses Well (USA)

The dredging project at the Morro Bay State Park marina is about two-thirds complete, reports sanluisobispo.com.

Eric Endersby, Morro Bay harbor director, said that these works are scheduled for completion around November 15.

We are removing about 33,000 cubic yards of material,” he said.

Overall cost of the project is $1.4 million with the dredging contract making up nearly $1.16 million, according to sanluisobispo.com.

[mappress]

Dredging Today Staff, October 24, 2012