NKT Completes First Campaign of Caithness-Moray Subsea Link

The NKT Victoria cable-laying vessel has laid the first HVDC cables in the Moray Firth as part of Scottish and Southern Electricity Networks’ Caithness-Moray transmission project.

The vessel completed its first campaign from Noss Head in Caithness to the midpoint of the cable route this week. It has now returned to Sweden to reload the remaining cable to be laid from Portgordon in Moray to the end of the previously laid cable later this month.

SSEN lead project manager, Brian Mitchell, said: “This is a major milestone for the Caithness-Moray project and I am delighted that the first cable laying campaign was completed on schedule. The vessel has now returned to Karlskrona in Sweden to load the remaining 56km of HVDC cable. A subsea joint will then be constructed to connect both sections of cable to complete the circuit.”

The Caithness-Moray project is required to transport renewable electricity from across the north of Scotland to areas of demand across Scotland and beyond.

The Caithness-Moray project is on schedule for completion in 2018, enabling a further 1,200MW of renewable generation capacity to connect to the grid.

The £1.1-billion project represents the largest investment in the north of Scotland’s electricity network since the hydro development era of the 1950s and is also the largest capital investment project undertaken by the SSE Group to date. It is also the largest Living Wage contract ever awarded in the UK.