NKT BorWin5

NKT installs power cables at TenneT’s BorWin5 offshore grid connection

Business Developments & Projects

Denmark’s NKT has finalized the installation of a 320 kV high-voltage DC (HVDC) power cable system at the 900 MW BorWin5 offshore grid connection in Germany.

Source: NKT via LinkedIn

The pull-in work to the offshore platform was carried out by the company’s NKT Victoria vessel.

NKT was responsible for the delivery and installation of 230 kilometers of 320 kV HVDC power cables under a contract signed with the Dutch/German offshore transmission system operator (TSO) TenneT in 2020.

The 900 MW BorWin5 offshore grid connection has a total length of 230 kilometers. The starting point is the converter platform BorWin epsilon, which was installed by Allseas in the German North Sea in May 2025.

There, the three-phase current generated by the He Dreiht offshore wind farm will be converted into direct current and transported to the mainland with an approximately 120-kilometer-long sea cable.

From the landfall in Hilgenriedesiel, the electricity will be transmitted along 110 kilometers of underground cable to the future converter station Garrel/Ost in the Cloppenburg area.

BorWin epsilon is expected to be commissioned by the end of 2025.

OE logo

๐๐จ๐ฐ๐ž๐ซ ๐˜๐จ๐ฎ๐ซ ๐๐ซ๐š๐ง๐ ๐–๐ข๐ญ๐ก ๐Ž๐Ÿ๐Ÿ๐ฌ๐ก๐จ๐ซ๐ž ๐„๐ง๐ž๐ซ๐ ๐ฒ โคต๏ธ

๐“๐š๐ค๐ž ๐ญ๐ก๐ž ๐ฌ๐ฉ๐จ๐ญ๐ฅ๐ข๐ ๐ก๐ญ ๐š๐ง๐ ๐š๐ง๐œ๐ก๐จ๐ซ ๐ฒ๐จ๐ฎ๐ซ ๐›๐ซ๐š๐ง๐ ๐ข๐ง ๐ญ๐ก๐ž ๐ก๐ž๐š๐ซ๐ญ ๐จ๐Ÿ ๐ญ๐ก๐ž ๐จ๐Ÿ๐Ÿ๐ฌ๐ก๐จ๐ซ๐ž ๐ฐ๐จ๐ซ๐ฅ๐!

๐‰๐จ๐ข๐ง ๐ฎ๐ฌ ๐Ÿ๐จ๐ซ ๐›๐ข๐ ๐ ๐ž๐ซ ๐ข๐ฆ๐ฉ๐š๐œ๐ญ ๐š๐ง๐ ๐š๐ฆ๐ฉ๐ฅ๐ข๐Ÿ๐ฒ ๐ฒ๐จ๐ฎ๐ซ ๐ฉ๐ซ๐ž๐ฌ๐ž๐ง๐œ๐ž ๐ข๐ง ๐ญ๐ก๐ž ๐ก๐ž๐š๐ซ๐ญ ๐จ๐Ÿ ๐ญ๐ก๐ž ๐จ๐Ÿ๐Ÿ๐ฌ๐ก๐จ๐ซ๐ž ๐ž๐ง๐ž๐ซ๐ ๐ฒ ๐œ๐จ๐ฆ๐ฆ๐ฎ๐ง๐ข๐ญ๐ฒ!