During the period 23 – 25 April 2013, the Petroleum Safety Authority Norway (PSA) carried out an audit of Eni Norge AS’ (Eni’s) work on ensuring compliance with requirements for establishment and implementation of technical and operational barriers in the development project on Goliat FPSO.

The objective of the audit was to follow up that Eni, in cooperation with HHI and other stakeholders, complies with the preconditions in the PDO, applicable regulations, standards, as well as Eni’s own requirements.

One nonconformity was identified in connection with barrier management.

No improvement items were identified.