10000 results found for 'progress'

10000 results found for 'progress'
Order results by

A list of search results

  • 21 December 2011

    The focus is offshore when it comes to renewable energy in Scotland, but the Scots figure that to really get the most out of the wind… By Pete Danko ( earthtechling ) [mappress] Source: earthtechling, December 21, 2011

  • 26 December 2012
    Business & Finance

    In December 2012, the two 16m tugs ordered by Boustead, Langkawi Shipyard, are being built simultaneously inside a modern fabrication shop. Macduff have provided the complete design package and cutting information for the tugs. Macduff Ship Design has risen and expanded steadily to become one of the most prolific naval architect / ship design marine […]

  • 16 December 2013
    Business & Finance, Equipment, Technology

    Maintenance work on the southern breakwater at the Mackay Marina has been progressing well and is currently on track to be completed by the scheduled date of mid-February, announced nqbp.com.au. Work will cease for two weeks over the Christmas – New Year period and the breakwater will be partially reopened for pedestrian access between Saturday 21 […]

  • 20 April 2012

    Good progress has been made on salvage activities this week. Heli-lifts yesterday removed four 40ft empty containers which were put onto the Pohonui. Another vessel was filled with debris from 14 different containers, one 20ft container was filled with scrap Today’s activities on the Rena continue with cutting of 3C cargo hatch and lashing of […]

  • 28 June 2011

      The latest significant expansion of Lerwick Harbour’s already extensive deep-water infrastructure is progressing towards completion around… (fishnewseu) [mappress] Source: fishnewseu, June 28, 2011;

  • 7 June 2012

    The work on new Baku International Sea Trade Port complex in Alat settlement located 65 km south from Baku is progressing according to the schedule. Deputy Transport Minister Musa Panahov has informed that work on the port construction is underway and to date dredging work has been finished by about 60%. He said: “Civil work […]

  • 18 June 2010

    Sri Lanka Ports Authority said yesterday the Oluvil Port Project has recorded a rapid progress of construction during the recent past… [mappress] Source: dailymirror, June 19, 2010;

  • 21 November 2012

    PETRONAS Canada and Progress Energy Resources said that PETRONAS Canada has exercised its right under the arrangement agreement between the parties to extend the “Outside Date” under the agreement to December 30. The Outside Date was originally established as October 31 and subsequently extended to November 30, 2012.  Under the agreement, PETRONAS Canada has the right to extend the […]

  • 1 May 2012

    The Jharkhand State Electricity Board (JSEB) has initiated an ambitious proposal to desilt the Getalsud reservoir. ”We have forwarded a proposal to carry out desilting of Getalsud Dam to the drinking water and sanitation department. Since the dam falls under their jurisdiction, JSEB would need a formal go ahead. Once a formal approval is obtained, […]

  • 20 December 2021
    Business & Finance, Business Developments & Projects, Certification & Classification, Environment, Outlook & Strategy, Regulation & Policy, Transition

    11 out of 23 ship finance portfolios are aligned with the International Maritime Organization’s (IMO) decarbonization target. In 2020, only 20% of reporting signatories were aligned with this goal, according to a new Poseidon Principles report.

  • 17 March 2011

    St. Augustine Port, Waterway & Beach District board of directors voted this week to contribute $500,000 of its reserves to the dredging… By PETER GUINTA (staugustine) [mappress] Source: staugustine, March 17, 2011  

  • 2 April 2013

    Rio Tinto has taken a major step forward in its expansion of its Pilbara operations, with the installation of the new shiploader with a nominal 55 million tonne annual capacity on the new wharf at Cape Lambert. The shiploader was swung from the ‘BigLift’ vessel and placed directly on to its rails on the wharf, […]

  • 21 December 2017
    Ports & Logistics

    Cheniere’s Corpus Christi liquefaction project located on the U.S. Gulf Coast has reached 77.4 percent completion. 

  • 26 December 2017
    Ports & Logistics

    Cheniere’s Sabine Pass LNG project in Louisiana, currently the only such facility to ship U.S. shale gas overseas, progressed with the construction activities during November. 

  • 10 January 2013

    Joe Oliver, Canada’s Minister of Natural Resources, released the following statement regarding TransCanada Corporation’s announcement it has been selected by Progress Energy Canada Ltd. to design, build, own and operate the proposed $5 billion Prince Rupert Gas Transmission Project. Canadian government welcomes proposals for resource projects – subject to proper regulatory review – that increase […]

  • 8 June 2014
    Business & Finance, Equipment, Technology

    A major repair project of the north jetty at Barnegat Inlet, which protects the southern tip of state-owned Island Beach State Park in Ocean County, is currently underway, Department of Environmental Protection (DEP) Commissioner Bob Martin said. Earlier this year, the U.S. Army Corps of Engineers’ Philadelphia District awarded a $7.6 million contract for the […]

  • 29 September 2013

    Australian shipbuilder ASC continues with the assembly of the first Hobart Class air warfare destroyer (AWD). The total number of blocks lifted onto the ship structure now stands at 22 with Block 417 lifted into place earlier this month. Block 417 will eventually carry the MK 45 Mod 4 5 inch 62 calibre gun, the […]

  • 14 January 2022
    Business Developments & Projects, Heavy lifting, Operations & Maintenance, Outlook & Strategy, Ports & Logistics

    French tidal energy company Sabella has ramped up the construction of its assembly facility in the Port of Brest ahead of operations planned for TIGER project.

  • 13 May 2014
    Business & Finance, Equipment, Technology

    Plans to help prevent significant flooding in parts of Somerset and improve the county’s roads moved a step closer this week after a key decision. Proposals totalling more than £20m were rubber-stamped yesterday by Councillor Harvey Siggs, Somerset County Council’s Cabinet member for Highways. Councillor John Osman, the Leader of Somerset County Council, last month […]

  • 6 July 2016
    Business & Finance

    Burnham Associates, Inc. of Boston (MA) has just announced that the construction works on the company’s new 3,000 CY split hull dredge barge are entering the final phase. The vessel to be named THOMAS DESMOND is being built at Sterling Shipyard of Port Neches, TX, USA. The newbuild will be utilized by its owner, and others, to support dredging projects […]

  • 18 April 2016
    Business & Finance, Equipment, Technology

    Gator Dredging, a Florida based dredging contractor, is now at 50% completion of the muck removal from Turkey Creek, located in Palm Bay, FL. Part of the larger Indian River Lagoon cleanup effort in Brevard County, this project involves dredging over 235,000 cubic yards of muck using an Ellicott 670 dredge called ‘Jesse Marie’. The […]

  • 24 May 2017
    Business & Finance, Operations & Maintenance, Research & Development, Technology

    The MORE team of the Centre for Marine and Environmental Research (CIMA) from the University of Algarve is finalizing preparations for the deployment of the scaled Evopod tidal energy unit as part of the SCORE project.

  • 13 September 2013
    Business & Finance

    The U.S. Environmental Protection Agency, the U.S. Army Corps of Engineers, the U.S. Fish and Wildlife Service, the State of Wisconsin, and Brown County announced that they are wrapping up work on the foundation for the Cat Island chain restoration project in Lower Green Bay. “Thanks to the Great Lakes Restoration Initiative – and our […]

  • 15 August 2014
    Business & Finance, Equipment, Technology

    According to the Environment Agency, the dredging program on the River Parrett near Moorland and the River Tone near Burrow Mumpon is moving ahead. “We continue to work on the River Parrett between Westonzoyland Pumping Station and Raymonds Farm and further upstream between Home Farm and Fenners Cottage along Riverside in Burrowbridge. On the opposite […]

  • 28 June 2010

    The government says around 100 million cubic meters of earth and sand have been dredged during the ongoing projects to maintain the nation’s…   [mappress] Source: world.kbs, June 28, 2010;