USA: Magnolia LNG Wins DOE Approval for FTA Exports

Magnolia LNG Wins DOE Approval for FTA Exports

Liquefied Natural Gas Limited said that the Office of Fossil Energy of the Department of Energy (DOE), United States, has granted authorisation for Magnolia LNG to export up to 4 mpta of LNG, from its proposed LNG project site at the Port of Lake Charles, Louisiana.

The DOE authorisation is valid for LNG sales to commence within 10 years and is then for a period of 25 years from first LNG sales; which sales are permitted to all existing, and any future, countries that have, or enter into, a Free Trade Agreement with the Government of the United States.

The Magnolia LNG Project comprises the proposed development of an 8 mtpa LNG project on a 90 acres site, in an established LNG shipping channel in the La ke Charles District. The project is based on two 4 mtpa development phases, each phase comprising 2 x 2 mtpa LNG production trains, and will use the Company’s wholly owned OSMR ® LNG process technology.

The DOE authorisation, follows the Company’s recent si gning of a Site Option to Lease Term Sheet, with the Lake Charles Harbour & Terminal District (Port Authority. The Company is now:

  • Negotiating a definitive and binding Real Estate Le ase Option Agreement with the Port Authority, together with the agreed form of Lease to be executed on Magnolia LNG, LLC exercising the site Lease Option;
  • In discussion with a number of parties who have expr essed interest to enter in to a Tolling Agreement, under which the Tolling Party will be responsible for arranging gas suppl y to the Magnolia LNG Project and the LNG buyers and ships. The Magnolia LNG Project will treat and liquefy the gas, store the produced LNG and load the LNG onto the LNG buyer’s ships, in consideration of a Capacity Fee and Processing Fee; and
  • Progressing work on the Magnolia LNG Project’s Pre File Application, which is required to be submitted to the Federal Energy Regulatory Co mmittee and represents the commencement of the project’s required permits and approvals process.

Managing Director Maurice Brand said “We are very pleased that the DOE authorisation had been received in accordance with the Company’s developmen t schedule. Our ability to meet key milestones will be a critical factor in discussions with potential Tolling Parties.”

[mappress]
LNG World News Staff, February 28, 2013; Image: LNG Ltd.