Cable installation for Shetland HVDC link to resume next month

Export cable installation to start at East Anglia Three offshore wind farm

Vessels

NKT, using its vessel NKT Victoria, is scheduled to start installing the export cable for the 1.4 GW East Anglia Three offshore wind farm in the UK this month.

The vessel is expected to mobilize from the port of Karlskrona in Sweden on June 14 and work on the East Anglia Three site 24/7, conducting simultaneous laying and burial of the cables, according to a Notice to Mariners from the project.

Offshore construction on ScottishPower Renewables’ East Anglia Three, located 69 kilometers off the coast of Norfolk, began this spring with the installation of monopiles.

NKT is supplying and installing the export cable for the project under a turnkey contract that the cable manufacturer secured in 2022.

In 2023, the company received a firm order from ScottishPower Renewables to design, manufacture, and install the complete 320 kV HVDC export power cable system for the offshore wind farm.

Related Article

East Anglia Three is the second of ScottishPower Renewables’ East Anglia projects to be developed and part of the East Anglia Hub, which includes two other offshore wind farms: the 800 MW East Anglia One North and the 900 MW East Anglia Two.

The 1.4 GW offshore wind farm will comprise 95 Siemens Gamesa 14+ MW wind turbines, all of which are expected to be operational in 2026.