BP gets nod to proceed with $262 M Vorlich field development

UK oil major BP has received approval from the Oil and Gas Authority (OGA) to proceed with the Vorlich development in the central North Sea.

The Vorlich field will be tied back to Ithaca Energy’s FPF-1 production platform / Image source: Ithaca Energy

The development, which will target 30 million barrels of oil equivalent, is expected to produce 20,000 barrels gross of oil equivalent a day at peak.

BP said on Thursday that the £200 million ($262 million) project was part of a program of North Sea subsea tie-back developments that seek to access important new production from fields located near to established producing infrastructure.

Vorlich, a two-well development approximately 241 kilometers east of Aberdeen, will be tied back to the Ithaca Energy-operated FPF-1 floating production facility, which sits at the center of Greater Stella Area production hub and around 10 kilometers from Vorlich. Ithaca has a 34% interest in Vorlich.

The field is expected to come onstream in 2020.

Committed to North Sea

BP North Sea Regional President Ariel Flores said: “BP is modernizing and transforming the way we work, with a focus on accelerating the pace of delivery of projects like Vorlich. Without compromising safety, we want to simplify our processes, reduce costs and improve project cycle time to increase the competitiveness of our North Sea business. This is increasingly important as competition for global investment funds gets stiffer.

“While not on the same scale as our huge Quad 204 and Clair Ridge projects, the Vorlich development provides another exciting addition to our refreshed North Sea portfolio and further demonstrates BP’s commitment to the North Sea.”

Scott Robertson, Central North Sea (CNS) Area Manager at the Oil and Gas Authority (OGA), said: “The OGA has been actively involved throughout the Vorlich project and is pleased to approve this development. The field will make an important contribution to our Maximising Economic Recovery UK (MER UK) priority as a valuable tieback utilizing existing infrastructure and by maximizing value from the Greater Stella Area hub.”

In April, BP announced its intent to develop Vorlich and Alligin, another project in its subsea tieback program. Alligin is a two-well development west of Shetland which will be tied back to BP’s Glen Lyon floating, production, storage and offloading (FPSO) vessel.

Alligin (BP 50% operator; Shell 50%) is a 20-million-barrel recoverable oil field in the Greater Schiehallion Area, located approximately 140 kilometers west of Shetland.