CTC Marine Continues Installation of Subsea Power Cables on BARD Offshore 1 Wind Farm (Germany)

CTC Marine has returned to Germany to continue the installation of subsea inter-array power cables on BARD Offshore 1 Wind Farm. The first array cable of the 2011 campaign has already been installed.

CTC is installing 80 inter-array power cables in total on the 400MW development located in the German Bight. The 2011 campaign follows on from last year and is expected to last up to 7 months. CTC is utilizing the Maersk Recorder mobilized with CTC’s CMROV 4 Jet Trenching ROV.

(subseauk)

[mappress]

Source: subseauk, April 11, 2011; Image: bard-offshore