DOC Delivers Trianel Borkum II Job

Tractebel DOC Offshore (DOC) has completed construction supervision of the inner array cabling for the Trianel Borkum II offshore wind farm (TWB II).

Picture: Trianel Windkraftwerk Borkum II GmbH & Co. KG: Cable laying in the offshore wind farm TWB II.

DOC has always provided the project with the required quality and number of representatives in a flexible manner, thus meeting our expectations in a targeted and satisfactory manner,” said the project manager responsible for cable installation at TWB II.

DOC supported the municipal offshore wind farm on the North Sea with up to 14 DOC offshore experts, from the loading of the cables, the necessary preparatory work on the transformer station and on the foundation structures, the subsequent cable laying and installation, to the connection work of the cables in the foundation structures and the concrete mattress installation for weighting the inner array cables.

Since mid-August 2018, DOC has been able to contribute its own core competencies to the completion of the inner array cable system. Communications with the project office on land and quality assurance were further components of the DOC work package.

The cable installation work was carried out with the Seaway Aimery, the Seaway Moxie, the Olympic Ares and the EDT Jane.

The cooperation on the construction site and with our client was without exception positive. We are proud that we could contribute our part to the Trianel wind farm Borkum II in the area of our core competencies“, states Oliver Spalthoff, managing director of DOC.