Dominion moves forward with Cove Point liquefaction project (Gallery)

Dominion filed a report with the United States Federal Energy Regulatory Commission on the construction progress of its Cove Point liquefaction project for the month of August.

Dominion revealed in its filing that the engineering component of the project is 94% complete while procurement and construction are 78% and 10% done, respectively.

During the review period, civil construction continued at offsite area A for grubbing, erosion and sediment control maintenance, mass excavation, installing of stone base, fine grading, and storm water management installation.

At the terminal, work continued on modifications to the existing plant by completing various utilities reroutes/modifications. Work included setting duct sections for the North and South HRSG, concrete placement for South STG foundation, and erected Tower Crane 4. Duct banks were also installed as well as medium voltage cable and underground fire water piping. Work continued on the demolition of select existing roads, cut/fill operations, setting sound wall columns and panels, and ongoing E&S control measures.

Work activities were performed on excavations, deep foundations, structure foundations, structural steel, setting sections of inlet ducting on the North and South HRSG’s, placing of North liquefaction; pedestals, tie beams, paving, form and pouring of the North steam turbine generator foundation.

Additionally, concrete placements for the North & South CT buildings, ACC pile caps, South CT pedestal columns, and North and South CT-C assembly table top formwork continued.

The Cove Point LNG export project is estimated to cost between $3.4 billion and $3.8 billion.

Dominion has fully subscribed the marketed capacity of the project with 20-year service agreements with ST Cove Point, a joint venture of Sumitomo Corporation, Tokyo Gas and Gail Global (USA) LNG.

[mappress mapid=”15750″]

LNG World News Staff; Image: Dominion